Ecosystem Restoration ER ER
ER
ER ER
Mineland ER Rangeland ER Storm Water
ER ER ER ER
ER ER
ER
Mineland
ER
Rangeland
Stormwater
ER
ER
Resources
ER
Contacts
ER
Sponsors
ER
ER
ER
ER

ER

Project Name: Bioengineered Streambank Stabilization on Silver Bow Creek

Project Start Date: April 1998

Project End Date: October 1999

County: Silver Bow

State: Montana

Nearest town: Butte

Silver Bow Creek Map

Estimated Cost:
Implementation costs for constructing the three basic types and eight variations of bioengineered treatments included toe material, willow bundles, fabric, excavator time and incidentals. Cost for incidental(s) included stakes, rebar, flags, micorrhizae, polymer, long sleeve rubber gloves, hard-hats, steel toe boots, waders, goggles, orange vests, rain gear and OSHA Certified Labor. Costs for travel, lodging, per diem and oversight are not included in the following breakdown.

An excavator and operator was used for five days to construct the four-foot deep trenches into which the willow bundles were placed at a cost of $6,000 plus $500 for mobilization (total $6,500). The cost of labor for planting was included in the cost per bundle of willows at $15. Therefore, the cost for planting 1,020 bundles for the three types and variations of bioengineered treatments was $15,300. A total of 32 biologs measuring 20 foot long and 16 inches in diameter were installed at five locations at a cost of $14 per foot ($280/log) for a total cost of $8,960. Erosion control fabric (COIR cf #7) cost $245 per role (120 sq.yd.) and $21.32 per role for installation (0.02 cents/sq. ft) for a total cost of $266.32 per roll. A total of 8 rolls measuring 6.6 inches wide and 165 feet long were installed for a total cost of $2,130.56.

Project Sponsor(s): Atlantic Richfield Company

Oversight Agency: U.S. Environmental Protection Agency

Project Partners: Project complexity dictated use of an interdisciplinary team approach including experienced professionals with expertise in civil and hydraulic engineering, hydrology, fluvial geomorphology, ecology, botany, bioengineering, habitat restoration, fisheries and other related disciplines. ESA Consultants Inc. under contract to the Atlantic Richfield Company (ARCO) developed the Work Plan, CDM Federal Programs Corporation, Inc. prepared depth to ground water and growth media placement maps, R2 Consultants Inc. produced the low flow channel design plan, Schaffer & Associates, Inc. developed the interim revegetation design plans, installed intensive vegetation treatment, conducted project oversight and monitoring, R. E. Miller contracted the harvesting and preparation of willows and Aquatic and Wetland Company designed and installed the bioengineered bank stabilization treatments.

Reasons for Action: The habitat value of Silver Bow Creek had been severely impacted due to mining activities at the Anaconda Mine.

Objectives: Create a healthy, functioning riparian ecosystem to compensate for impacts

History of Site: A portion of the Silver Bow Creek drainage basin near Butte, Montana was the site of a remediation project titled Lower Area One (LAO) Phase I, Segment II. Remediation included removal of large quantities of tailings and underlying soils with elevated metals concentrations. Clean fill material was imported to construct a 200 to 400 foot wide floodplain and a low flow meandering stream channel. Consequently, the project presented the need for: 1) creating a fully vegetated riparian floodplain corridor, 2) restoring biological function using bioengineered bank stabilization treatments, and 3) creating diverse fish and wildlife habitat.

Pre-Restoration Photos: No

Design Narrative: The newly configured channel extended 7,000 feet (1.325 mile) with 14,000 feet (2.65 miles) of riparian corridor that was planted with native grass species, herbaceous sedges and rushes, shrubs including willow (Salix spp.) and tree plantings. The planform of the low flow channel was designed with a sinuosity of 1.25 and typical stream gradients from 0.2% to 0.4%. The constructed channel included a top width ranging between 30 and 45 feet, a bottom depth of 2.5 feet, 1.75:1 side slopes and a capacity to transport 270 cfs before overbanking. Observation and map analysis resulted in identification of 30 outside concave curve banks and 30 point bars or inside convex curve banks. Each curve was numbered beginning at the downstream project boundary.

Careful consideration was given to stabilization of the streambank zone defined by the channel edge or bank toe, bank slope and floodplain terrace associated with the reconstructed channel. Five native willow species were identified for planting in the streambank zone based on their phenology-morphology, environmental tolerances and production characteristics (ARCO 1997). Three of the five species were known to be abundant within the Silver Bow Creek floodplain valley including Sandbar willow (Salix exigua), Booths willow (Salix boothii), and Yellow willow, (Salix lutea) and harvest sites were selected accordingly. Other willow species played a minor role and were not considered in the monitoring results discussed below: Geyers willow (Salix geyeriana), Pacific willow (Salix iasiandra), and Bebbs willow, (Salix bebbiana).

Bioengineered Treatments. Bioengineered bank treatments were located at 13 of the 30 outside concave bends. Three bioengineered designs were prepared and implemented based on the high and low risk erosion potential and named according to presence or absence of the material placed at the toe of the bank slope (Supplement 1, pdf). Toe material was considered nonstructural/organic and included wattling (live facines), brush layering (willow cuttings) and biologs constructed from biodegradable coconut fibers. A plan was developed to avoid subjecting the newly formed floodplain; riparian corridor and channel to the erosive overbank flows of spring snowmelt runoff and isolated storm events. An engineered diversion was located immediately upstream of the project site to divert flow of 35 cfs into an alternate channel in excess for a period of five years or until the concave banks became stabilized with native plant (i.e., willow) root structure. The diversion channel was sized to convey the runoff from the 10-year-24 hour storm event estimated at 477 cfs.

Construction Narrative: The initial work steps included harvesting, bundling, handling, soaking and planting willows. The project began by harvesting dormant willows during the early spring of 1998 and planting progressed thereafter during April, May and June.

Harvesting Willows. Small lightweight chain saws and heavy-duty brush cutters worked well for harvesting large numbers of willow stems in a short period. Once willows were cut near ground level, they were gathered and piled at a convenient site for processing.

Bundling. Processing willows for ease of handling included forming a bundle by gathering ten stems (plus or minus one inch in diameter). Dead stems were not included in the bundles. One person held a bundle of ten stems while a second person encircled the bundle with five wraps of plastic wrap that is then easily torn off. This was repeated for a second wrap. The bundles were placed in piles of ten, loaded onto a covered trailer to keep out of the sun and prevent drying and transported to a site for soaking in water.

Soaking. All willow bundles were placed in a pond and to the extent possible, submerged for a minimum of three days or longer. Soaking willows ensures that the vascular tissue and buds are super saturated and results in dissolution and leaching of an anti-root hormone located in the stems. After soaking, bundles were removed from the pond, transported to the construction site, placed in the creek's flowing water and planted the same day.

Wattling was used as the protective toe at five locations for a total 680 feet. A brush layer toe was installed at three locations for a total of 513 feet. A biolog toe was installed at five locations for a total of 650 feet. Therefore, the total bioengineered treatment length was 1,843 feet (0.35 mile).

An intensive vegetation treatment (IVT) was applied throughout the remainder of the corridor and included planting mini willow bundles, other shrubs and trees above the ordinary high water mark, sedges and rushes from the water edge throughout the capillary zone, and intra-seeding and hydromulching the remaining space. This treatment was applied to the remaining 17 low risk erosion potential banks, point bars and straight reaches (14,000' minus 1,843' equal 12,257').

Mini bundles of willow cuttings were inserted to the ground water table after punching a three to four foot deep hole with a dibble bar attached to the bucket of a rotating trackhoe. Three staggered rows on one-foot centers were planted along the concave bends and two staggered rows on one-foot centers were planted along the convex bend point bars and straight reaches. Planting distance from the water edge ranged between one foot and three foot. The number of cuttings placed in each dibbled hole varied according to the diameter of the cuttings and ranged between two and four.

Construction Photos:

 
 
 
 

Project Success: Second year monitoring indicated a highly successful stabilization project based on absence of erosion, vegetation survival, density, growth, and streambank stability. The design objectives have been met. The concave, convex and straight reaches of the streambanks are stable, riffle/run/pool habitat is present, several species of fish have been observed, waterfowl have become residents, deer have been migrating through the corridor and site aesthetics are rapidly developing. In channel habitat types are improving and maintaining themselves. Sediment is moving through the system with no major bed aggradation or degradation. Riffles have unearthed clean large gravel and cobble that are suitable for spawning. Riparian structure and habitat is developing at a rapid rate.

The Lower Area One, Phase I, Segment II should be an example project of how traditional nonfunctional hard riprap stabilization approaches can be replaced by biologically functional bioengineered approaches to erosion and bank stabilization challenges. Information and understanding gained from the variety of bioengineering designs used on this project will be considered during potential future designs downstream of Butte.

How was success determined? End of the first growing season monitoring during October 1998 included photography and qualitative observations. End of the second growing season monitoring during October 1999 included measurements of willow survival, density, and growth (Ave. and Max. height).

Willow Growth (Second Year) Average height and maximum height measurements were made at six of the thirteen- banks treated with the three different types of bioengineered treatments and their variations: wattle toe, biolog toe and brush layer toe (Table 1). Stem height was measured within each of three randomly selected one-meter sections for each of six bank treatments for a total of 18 meters (Table 2). The amount of growth was measured from the surface of the ground to the woody-growing tip of the stem. Branches and leaves were not measured.

Average height ranged between 4.0 and 4.6 feet for an average of 4.2 feet by the end of the second growing season. An average 77 day growing season (range = 74 to 80 frost-free days) was used to estimate the inches of growth per day for the two growing seasons. Average growth per day ranged between 0.33 and 0.38 inches per day or a little over one-third of an inch per day.

Maximum height for the fastest growing stems ranged between 6.8 and 8.6 feet in height and averaged 7.8 feet for the six banks measured (Table 2). Therefore fast growing stem growth for the two growing seasons ranged between 0.57 inches and 0.72 inches for an average growth rate of nearly two thirds of an inch per day (0.65"). A number of stems achieved a height of 8.6 feet (103.2") that translates into a growth rate of 0.72 inches per day by the end of the second growing season (77 days + 77 days = 144 days). Average willow stem growth under the conditions within the Silver Bow Creek valley on average grew one-third of an inch each day over the two growing seasons and the fast growing stems averaged nearly three-fourths inch per day. Although not evaluated, it was assumed that the amount of stabilizing underground root growth equaled the amount of above ground production.

Mortality/Survival Planting Density. Interest was expressed regarding the number of willow stems planted per meter for the installed variations of brush layering. Therefore three one-meter sections were randomly selected within six of the treatment types (18 meters). The number of live stems and dead stems were counted. The number of willow stems planted per meter did not vary greatly for the six banks sampled. Average number of stems surviving per meter at the end of the second growing season within the six treatments was 16.3 or 64% of those planted (Table 3). Average number of dead stems counted was 9.3 (36%) suggesting that the average number of willow stems planted per meter was 26.

Bank Stability-First Growing Season Successful stabilization was judged by two criteria: 1) an unpredictable storm flow and 2) quantitative measurements.

An estimated flow of 450 cfs occurred following a severe thunderstorm on July 31,1998 or approximately three months after treatment implementation. It was estimated that 300 cfs was diverted into the alternate channel and 150 cfs remained in the new Silver Bow Creek channel. Minimal erosion damage was observed and no repair work was required. Therefore, it was concluded that the bioengineered treatments worked well at the design flow capacity.

Quantitative measurements based on erosion, stem survival/mortality, density, above and below ground growth suggested that each treatment produced greater than satisfactory subsurface root structure and above ground woody stem structure. Willow clumps could not be pulled from the ground at the end of the first or second growing season. No erosion was observed in the 17 concave bend areas treated with IVT.

Although quantitative measurements were not taken, species differences in willow phenology/morphology and production characteristics contributed greatly to bank stabilization. Sandbar, Booths and Yellow willow cuttings each formed roots within 10 to 15 days of planting. Banks were well stabilized during the first growing season and improved significantly by the end of the second growing season. It was assumed that the amount of above ground growth was reflected in the amount of below ground root growth. Biomass production was rated high when compared to other members of the same lifeform. Observations suggested that Booths and Yellow willow cuttings out performed Sandbar willow in terms of short and long-term above ground vegetative production. Therefore, Booths and Yellow willow cuttings can be highly recommended for future stabilization projects scheduled for the Silver Bow Creek valley

For more information on this project, contact:

Jay Windell
Aquatic and Wetland Company
9999 Weld County Rd. 25
Ft. Lupton, CO 80621


Phone: 303-442-4766

E-mail: jay@aquaticandwetland.com

URL: http://www.aquaticandwetland.com/

OR

Chuck Stilwell
ARCO
307 East Park Street, Suite 400
Anaconda, Mt. 59711

Available Documentation:

Table 1. Bank number, treatment type and length
Table 2. Number of willow cuttings planted per meter, and number and percent survival
Table 3. Willow cutting growth at end of second growing season
Table 4. Cost per foot comparison of bioengineered and riprap treatments. Costs assume completion of bank shaping /grading; all treatments extend up the bank.

Submitted by:

Susan Cousins
Aquatic and Wetland Company
1830 17th Street, Suite 100
Boulder, CO 80302


Phone: 303-442-5770

Email: susan@aquaticandwetland.com

Date: August 23, 2000

 

ER

Case Histories | Photo Tour | Tech Guide

ER
ER
ER