Ecosystem Restoration ER ER
ER
ER ER
Mineland ER Rangeland ER Storm Water
ER ER ER ER
ER ER
ER
Mineland
ER
Rangeland
Stormwater
ER
ER
Resources
ER
Contacts
ER
Sponsors
ER
ER
ER
ER

ER

Project Name: Anaconda Revegetation and Treatability Study (ARTS) Site 9 Smelter Hill, Anaconda Montana

Project Start Date: 1992

Project End Date: 1997

County: Deer Lodge

State: Montana

Anaconda Smelter Superfund Site

Nearest town and distance: Immediately adjacent to the town of Anaconda, MT

Project Partners: Atlantic Richfield (ARCO), Montana Department of Environmental Quality, EPA, Research and Development Institute

Objectives: Development and demonstration of in-situ reclamation technologies for the Anaconda Smelter Superfund Site. Five field demonstrations of in-situ treatment of contaminated soils were conducted ranging in size from 1-5 acres.

History of Site: The Anaconda Smelter Site was the principal location used by the Anaconda Minerals Company for processing the ores derived from the mines in Butte Montana. Smelting of copper rich ore was originally conducted in Butte, but was later moved 20 miles away to Anaconda where water was more abundant. The original smelter sites called the Old Works (now a Jack Nicholas designed golf course) was the site of smelting from the 1880's until the turn of the century when the smelting operation was moved across the valley to the present location. The smelter stack pictured was constructed in 1918 and operated until 1981. Tons of sulfur dioxide and arsenic trioxide were released from the stack during operation in addition to tons of copper, zinc, lead and other metals. Following closure of the operation in 1981 the structures on the hill were razed in 1983 leaving only the stack as a remnant of the historic operation. The site was listed by the EPA on the National Priorities List. Remedial action is presently being designed for the site.

Pre-Restoration Photos:

Sparsely vegetated landscape contaminated with As, Cu, Zn, Cd, and Pb. Marginal vegetation results in significant erosion and release of contaminants to the environment

Contaminated material is amended with composted manure and fertilizer in greenhouse trials for evaluation of amendment rates and species selection for seeding

Design Narrative: Laboratory, greenhouse and field evaluations were conducted to assess which desirable plant species were invading the site and how soil chemical and physical properties could be altered through treatment to allow more extensive establishment of native vegetation. Based on careful laboratory analysis and successful greenhouse trials a field design was developed and implemented in the fall of 1992.

Construction Narrative: A 150 foot by 1400 foot rectangular test plot was laid out running the length of Smelter Hill. Existing erosional gullies and an abandoned rail line were demolished and re-graded. A 0.77 acre acidic area (apparently related to a spill of ore concentrate below the rail line) was limed with a weathered lime product remaining from operation of the smelter. Composted manure was hauled to the site and incorporated to an 18 inch depth with a modified Baker plow. Dozer basins and gouges were installed to control storm water runoff during plant establishment. The site was mulched with straw mulch, crimped into the soil and seeded with a native grass mixture. High rates of phosphorous fertilizer were also applied to the site in addition to nitrogen and potassium.

Construction Photos:

Regrading of the test plot removed erosional gullies and an abandoned railroad grade
A portion of the area was contaminated by an ore concentrate spill resulting in low pH soil conditions in addition to contaminants deposited by aerial fallout. Lime addition was required to ameliorate soil acidity. The lime spreader was cabled to the D8 dozer for safe application on the steep slope
Lime application occurred over 0.75 acres of the 5 acre test plot
Amendments were incorporated by a large disc plow

Supplementary Narrative: Subsequent to construction of the site, monitoring was conducted to assess the effectiveness of the treatment. Monitoring included runoff quantity, climate, vegetative success, soil chemistry, rate of sedimentation of gouges and dozer basins and soil water movement. The result of the project (in addition to the other 4 ARTS Sites) formed the basis for EPA's selection of Land Reclamation for approximately 10,000 acres of the site at a projected cost of $180 million. The risk to wildlife species using in-situ technology is presently being evaluated through population and toxicological study of small mammals and avian species using this test plot.

Post Remediation:

Vigorous vegetation dominated by native grasses (Lemous cinereus--Basin wildrye) was established following treatment. Erosion was greatly reduced. After 7 growing seasons the vegetation continues to thrive

For more information on this project, contact:

Reclamation Research Unit Montana State University
106 Linfield Hall
Bozeman, MT 59717


Phone: (406)994-4821

E-mail: dneuman@montana.edu (Principal Investigator)

URL: http://agadsrv.msu.montana.edu/reclamation/

Available Documentation: Multiple documents are available which summarize this work. The principal documents are Phase I: Site History and Literature Review, Phase II: Laboratory and Greenhouse Studies, Phase III Field Implementation and Phase IV Monitoring and Final Report

Submitted by: Stuart Jennings

Date: July 13, 2000

 

ER

Case Histories | Photo Tour | Tech Guide

ER
ER
ER