|
Moon Gulch Mine,
a.k.a. Silver Crescent Mine or Moon Creek
$1.9 Million
 |
| Moon
Gulch Mine Before Reclamation |
|
 |
County:
Shoshone State: Idaho
Approximately
5 miles northeast of Kellogg, Idaho
 |
| Location
of Moon
Gulch Mine |
|
U.S. Department of Agriculture, Forest Service
(USFS) under provisions of the U.S. Comprehensive Environmental
Response
Compensation and Liability Act (CERCLA) as a non-time critical removal
action. The Forest Service is the lead federal agency addressing sites
with uncontrolled hazardous substances located on National Forest Lands.
- Characterization - U.S. Bureau of Mines (USBM)
- Design / Consulting
- Ridolfi Engineers
- Construction Contractor - Environmental Reclamation,
Inc.
Ridolfi Engineers (text)
Seattle, Washington
info@ridolfi.com |
Jeff Johnson, Geologist (photos and charts)
U.S. Forest Service – Region 1
Panhandle National Forest |
- Release of lead, zinc, cadmium, copper, mercury,
and arsenic from the site
- Dissolved and suspended load of Moon Creek
- Human Health Hazard
- Near a residential area
- Popular recreation site
The potential
for human, fish, and wildlife exposure to elevated metals concentrations
from
materials remaining
on-site. Lead and zinc
were
the primary contaminants of concern for reclamation planning.
The
goal of the project was to reduce the release and threat of release
of hazardous substances from the site, thereby reducing
risks to human
health and the environment. The objectives of the reclamation plan were to:
(1) achieve the CERCLA non-critical removal action; (2) develop an area that
is safe
for human health; (3) rehabilitate the stream and adjacent riparian area
to support Westslope cutthroat trout.
The site is located
on the East Fork of Moon Creek on federally owned lands within
the Idaho Panhandle National Forest in Northern Idaho.
The project site is an abandoned mine and mill complex that was operated
as part
of the Coeur d’Alene Mining District. The complex includes the Charles
Dickens Mine, which operated from 1902 until 1930, and the Silver Crescent
Mine and Mill that operated from 1911 to 1954. The mine facility includes
at least
four adits, two shafts, and several miles of underground workings. These
mines together produced 4,606 tones of ore. Metals production from the Moon
Creek
mine complex was primarily lead and zinc, with limited silver, copper and
gold.
The Silver Crescent Mill was initially operated as a jig-type
mill, but flotation circuits were added in the early 1920s. The
resulting tailing
deposits include
the coarser-grained, higher-concentration jig tailings and the finer textured
flotation tailings. The Silver Crescent Mill was a custom mill that produced
ore from several off-site mines in the Coeur d’Alene Mining District.
Therefore, the volume of tailings on site is proportionally greater than
would be expected
given the production from the mines on site. The volumes of tailings and
other mine waste material remaining on site are summarized below.
Flotation
Tailings 69,000 CY
Mine Waste Dumps
- Main Dump 21,900 CY
- North Dump 5,800 CY
- South Dump 400 CY
Mixed Soils and Tailings 30,500 CY
TOTAL 128,100 CY
- Mine and Mill site approximately 20 acres
- Elevation range on the
site 2,600ft to 2,800ft
- Temperature ranges from –2F to 100F
- Rainfall approximately
40 in/yr
- Watershed size is 3.28 square miles with 2.73 square miles
above the site
- Base flow of East Fork Moon Creek is approximately
0.5cfs (8.8cfs peak 1993)
- Precambrian Prichard Formation of the Belt Supergroup
- Consists
of thick bedded quartzose argillite and argillite
- Pb, Zn, Ag Ore
came from the Middle Prichard argillites – pyrite, sphalerite,
galena
The
initial site characterization was conducted by a multi-discipline,
multi-agency teaming that included engineers, scientists, and forest
managers from the USFS, the U.S. Bureau of Mines (USBM), and Ridolfi
Engineers. Concurrent environmental sampling, survey, and riparian
inventories were obtained to allow an understanding of not only the
contaminant pathways, but also the environmental conditions with
respect to vegetation, water and soils. This collaboration allowed
early concept development to integrate ecological principles into
the engineering design for stabilizing and rehabilitate the site.
In this way, the site environmental conditions, multiple methods
for removing and isolating the contaminants, and methods for stabilizing
the site that would enhance recovery could be evaluated considering
the goals for the mine reclamation.
The USFS, the U.S. Bureau of Mines (USBM), and
Ridolfi Engineers conducted sampling and monitoring at the site.
Surface water data collected at the monitoring station downstream
of the site indicated that at low-flow conditions, mean concentrations
of cadmium, copper, lead, and zinc exceeded background concentrations,
Federal Water Quality Criteria or safe drinking water maximum contaminant
levels. Ground water data collected from monitoring wells down gradient
of the mill site showed arsenic, cadmium, copper, and lead in excess
of federal drinking water standards. Seeps along the stream banks
indicated a pathway for ground water to enter the creek.
Extensive soil sampling was conducted throughout the site including
the waste dumps, upper mine area, lower mill area, and flotation
tailings piles. Soil sample results from the mine waste dump areas
indicated that arsenic, copper, lead, zinc, and mercury exceeded
background or ecological effects levels by several orders of magnitude.
Sample results from the upper mine area and the lower mill area showed
contaminant concentrations that exceeded background and ecological
effects. Samples taken in the flotation tailings areas showed mean
concentrations of antimony, arsenic, copper, lead, zinc, and mercury
that were greater than background and ecological effects levels.
- Reduce the release of lead, zinc, cadmium,
copper, mercury, and arsenic to Moon Creek
- Rehabilitate the site,
limiting exposure pathways
- Improve cutthroat habitat
Through
the site characterization effort, several opportunities and constraints
were identified
that helped shape the reclamation
plan for this site. The valley geometry presented both an opportunity
and a constraint in that the site is located within a fairly
steep
(3-5
percent slope) and narrow
valley. The opportunities were presented by well-forested, healthy
hillsides adjacent to the site that serve as shade for the stream
and a source
of colonization for vegetation. The constraints were posed
by the
need to find a suitable
area on site to locate the waste containment.
An existing
site road served as a source of sediment to the stream. Because
the road was adjacent to the stream,
and
had existing vegetation, it provided
an
opportunity to remove the road, and re-locate the stream.
Westslope
cutthroat trout (Onchrynchus clarki lewisii), a candidate species
for listing under the Endangered Species Act were identified
in upstream
reaches above the mine and mill site. This provided opportunities
with respect to shaping
the final stream channel, and constraints with respect to construction
scheduling around fry emergence.
Moon Creek passed through the
mill site, physically bisecting the tailings impoundment. There
were several seeps in the vicinity
of the mill site.
The floodplain in
both the upper mill area, and the tailings impoundment did not
support vegetation, and previous revegetation efforts had failed.
However,
metals concentrations
do not increase through the reach passing through the tailings,
and lysimeters in the tailings indicated low ground water flow
rates
to the stream.
From the identification of possible opportunities
and constraints, considerations for the reclamation design were
to: (1) use existing
features to the
greatest extent possible; (2) develop an innovative and effective
waste containment
design; (3) rehabilitate the steam to provide fish habitat,
and (4) use bio-engineering methods for site stabilization.
Existing features
that could be used in reclamation included the narrow valley geometry,
forested hillsides, boulders, the narrow road through the site, and
on-site vegetation. The new stream alignment was based upon maintaining
part of the existing riparian area and providing cover for the stream.
The narrow valley and heavily forested sides slopes contributed to
this goal. Trees and boulders within the area to be disturbed outside
the contaminated areas were identified for salvaging and re-use in
stream habitat measures. The road embankment through the site contained
a significant quantity of clean rock and soil that was used for fill
in constructing the floodplain and waste containment. In the upstream
reach, the stream was relocated to the previous road alignment. This
allowed for better sequencing during reclamation. Removing the road
also eliminated an existing source of sediment to the stream. On-site
vegetation was used as a source of seed and cuttings for native planting.
Vegetation from clearing and grubbing operations was composted on-site
and used for soil amendment. Consolidating and isolating the mining and milling waste
posed the greatest challenge for this project. The solution depended
upon an innovative waste containment design. Based on synthetic
leach testing of the on-site materials and modeling of the cover
elements, it was determined that the on-site wastes were compatible,
and that the potential impacts from leachate containing elevated
metals concentrations were limited. Therefore, the waste rock,
jig and flotation tailings, and soils containing elevated metals
concentrations were consolidated into an unlined combined waste
facility. The combined waste facility is long and narrow to fit
into the valley section and allow a stream buffer; the combined
waste facility is approximately 800 feet long by 150 feet wide,
and 27 feet in height.
Design considerations and key components of the combined waste containment
included physical location, a compacted gravel drain system, geocell
mattress, subgrade scour protection berm, and water balance cap to
prevent surface water percolation through the waste material into
the containment. The containment is located within the middle flotation
tailings area with one edge benched into the valley wall and a portion
of the containment base located on top of the tailings. The benches
have been meandered into the existing hillside to soften the appearance
of the containment, and to maximize storage volume. Placing the containment
on the tailings limits the material excavation costs; however, it
presents several design challenges related to soft foundation conditions.
Typically the geotechnical solutions for soft foundations include
reduction of pore pressure, installation of lateral stability measures,
and placement of a surcharge prior to loading.
The design for the combined waste containment base incorporated features
that perform all three functions. A compacted gravel drain system
is provided along the periphery of the containment with lateral headers
on an 80-foot spacing. This drain provides a preferential drainage
path for in-situ ground water. A common sewer cleanout is used at
the upper ends of this drain system to allow future monitoring of
the containment base. Limestone gravel was placed in the lower portion
of this drain to attenuate any metals present in pore-water drainage.
The initial layer in the containment is comprised of a geocell mattress.
This is an eight-inch thick, three-dimensional perforated polyethylene
web (Geoweb™) system that is carefully backfilled with waste
rock. A geocell mattress has been shown to provide lateral stability,
and a surcharge prior to load placement for similar soft foundation
conditions.
A five-foot deep impervious scour protection berm provides lateral
stability during construction and support for the compacted gravel
drain and in-situ tailings within the containment base. The external
face of this berm is armored with riprap to provide protection from
future stream erosion, should the stream meander toward the containment.
This berm also limits ground water intrusion into the containment.
Within
the containment, the waste will be mixed for homogeneity. A mid-height
gravel drain is included to help de-water
the in-situ waste within the upper lifts of the containment.
The
Hydraulic Evaluation of Landfill Performance (HELP) computer model8
developed by the U.S. Environmental Protection Agency (EPA)
was used to optimize the water balance cap design for the containment.
This cap features two feet of growth media underlain by a gravel
drainage layer. A combination of evapo-transpiration from the vegetation
and a capillary break between the soils and the underlying gravel
act as the primary means of preventing surface water percolation.
A geosynthetic clay liner with underlying cushion material (sand)
has been included to further reduce surface water infiltration.
These innovative measures combine to allow an on-site waste containment
design that effectively isolates the mine waste materials found
on
the Moon Creek site. Stream rehabilitation measures focused on
providing suitable habitat to support Westslope cutthroat trout,
a fish native to the Moon Creek watershed. The considerations and
components of the stream rehabilitation for the Moon Creek project
include stream location, a constructed wetlands buffer, microhabitat,
and substrate placement.
The new channel for Moon Creek was relocated into the existing road
area in the upper segment of the site, and into the base of the hillside
in the lower segment. The middle segment passes through the existing
mill area.
The new channel section was designed to accommodate the
bank-full flow, which is approximately a 1.5 year frequency storm
event. The
channel was designed with input from USFS fish biologists, and
using Idaho Fish and Game Habitat Curves. Because the valley slope
of three
to five percent is greater than the slopes presented in these curves
as optimal for this species, microhabitat in the form of in-stream
spawning substrate material, large woody debris, and boulder pools
were included to enhance habitat for trout. Because of extensive
removal in the existing valley, clean fill was imported to reconstruct
a floodplain outside of the main channel. Meanders following existing
patterns on site and based on reference areas immediately upstream
of the site were used for the new stream layout. In general, the
channel was designed as a "deformable boundary channel" to
allow natural geomorphologic processes to perform the majority
of the channel shaping. Bank protection using bio-engineering methods
were be used at the two junctions with the existing stream section.
Bio-engineering
measures were included into the design to provide a natural self-sustaining
means to stabilize the site. These measures included cutstakes with
coir
fabric for stream banks, willow wattles for flood erosion control,
block planting, and bio-filters for erosion and sediment control.
Willow cut stakes were placed on 18-inch centers through an anchored
coir fabric mat to provide protection for the three key bank
areas along the new stream channel. Meandered willow wattling
were installed
on a 50-foot spacing along the over-banks, to trap surface
sediment, direct flows back to the channel, and provide upland niches
for
wildlife. Vegetation between the wattles were established using
staggered block
plantings. This involved random placing of 16 to 20 containerized
plants into a 15-foot by 25-foot area. Block plantings allow
shade between plants, and colonization of other areas by wind,
water,
and animal vectors. Native plant species selected for these
block plantings
include shrubs and mid-story trees appropriate for the elevation
and climate found at this site. Hardiness (western cedar),
litter production (cottonwood, aspen), nitrogen fixation (alders)
and
wildlife preferences (mountain ash, elderberry, snowberry)
were additional
considerations used in the plant selection process.
Because
of the length of the disturbance to the vegetation on-site, it
is anticipated that there may be an extended period
for the
plant communities to recover. Soil amendments and composted
vegetation from on-site clearing were used to augment the
existing soils.
It
is anticipated that over time, the conifers from the adjacent
slopes will colonize to the site. A grass-forb mixture was
used to seed
the remaining bare areas between the blocks and the existing
vegetation. The slopes remaining after the waste rock was
removed were stabilized
using vegetation and bio-filter bags. These are recycled
plastic mesh tubes each about five feet in length and filled with
recycled
wood chips. These bags are installed by staking into the
slope on a 20-foot spacing, similar to wattling. In addition to sediment
trapping
ability, the wood chips form a weak ion exchange agent that
may attenuate metals remaining in the surface sediment. |