Ecosystem Restoration ER ER
ER
ER ER
Mineland ER Rangeland ER Storm Water
ER ER ER ER
ER ER
ER
Mineland
ER
Rangeland
Stormwater
ER
ER
Resources
ER
Contacts
ER
Sponsors
ER
ER
ER
ER

ER

Project Name: Maxville Tailings Removal and Londonderry Mine Reclamation Project

Project Start Date: October 1, 1996

Project End Date: Construction was completed except for mulching and seeding on December 3, 1996. Mulch and seed were applied and site work was completed on May 20, 1997.

Location:  Maxville, Montana.  For directions to Maxville, click on the Icon.  For an online GIS environment with downloadable maps, go to the Montana Natural Resource Information System and pick the town name "Maxville".

Directions to Maxville: (Supplement 1)

Maxville Tailings/Londonderry Mine Before Reclamation

Site Cleanup Summary: The primary elements of concern at this abandoned hard rock mine site included three waste rock dumps, one acid producing tailings pond, and one adit discharging contaminated water into a nearby creek. The tailings pond had also intermittently been used by Granite County as a solid waste disposal dumpsite. Arsenic, lead, and copper were determined to be creating adverse ecological effects for fish, wildlife, and plants in the area. Arsenic was present at concentrations high enough to create a human health risk for the current open space land use. Although cyanide leaching was used in the  mining process, concentrations of cyanide in the tailings material were found not to significantly exceed background levels in nearby soils. Road access was limited for a large portion of the site, and consequently access roads and a bridge over Flint Creek had to be built in order to reclaim the area. One of the three waste rock dumps and both of the tailings ponds were excavated, moved to a modified RCRA landfill and capped in place. One of the waste rock piles was regraded, lime was incorporated to 12 inch depth, and the dump was recontoured, fertilized, and revegetated. The smallest waste rock dump was not an acid producer and was becoming well vegetated, thus it was not reclaimed.  Water from the adit discharge remains untreated at this time.  

History of Site: The historic Maxville Mining District has produced relatively large quantities of silver, gold, zinc, lead, copper, and manganese. The first lode was discovered at the Hope Mine in 1864 with other nearby areas following soon after. The most active period of mining in this area was from 1881 to 1893. In 1887, the Northern Pacific Railroad completed the Philipsburg branch, which passed within 70 yards of the Londonderry Adit, allowing ore to be moved to a smelter via rail. The nearby, larger Durand Mine began operation in 1892. The Londonderry Mine is described as being active as early as 1913, when five rail cars of ore were shipped yielding $6.50 of gold and 50 ounces of silver per ton of ore.

From 1921 to 1924, the Londonderry Mine was operated by the Maxville Gold, Silver and Development Company, but the property may have been idle. From 1926 to 1927, the company expanded operations by installing a 100-ton per day floatation mill on public land located approximately 50 meters north of the adit. Facilities were also constructed on adjacent private land (east side of Flint Creek). With the new mill site in place, the Londonderry Lode expanded to 1,900 feet of horizontal adit tunnel and 300 feet of vertical shaft with 1,500 feet of workings on three levels. Ore was moved to the surface with rail mounted ore cars. The ore was loaded into a series of hoppers and transferred to the nearby railroad for transport to the smelter. The winter of 1930 was the last known year of production. Little is known of the method of mining or where the ore was shipped for processing.

By the early 1930's, the mine was leased to Mr. Richard Valiton. In April 1936, a mineral survey was completed to patent the Londonderry Lode to Mr. W.E. Albright. This survey shows that Mr. Albright had five tunnels, two raises, and one cut within the proposed patent area. In 1938, the Londonderry Lode claim was willed to Mr. Albright's daughter in probate following his death. In 1939, the Londonderry Lode claim passed from federal to private ownership as allowed under the 1872 General Mining Laws. President Franklin D. Roosevelt granted Patent #1100918 to Ms. Alta M. Patten of University City, Missouri, in 1939. The Londonderry Adit is not shown in this patent because the adit entrance is located 31.7 feet to the east on BLM (public) lands. The Londonderry Adit entrance remains in federal ownership.

In 1988, contaminated water was observed discharging from the Londonderry Adit into Flint Creek. Water quality data indicated high levels of arsenic, bicarbonates, barium, calcium, cobalt, iron, magnesium, manganese, cadmium, and zinc in the discharge. Associated waste rock along the west bank of Flint Creek also contained elevated levels of heavy metals and was contributing sediment into Flint Creek.

In 1990, the BLM hired an environmental consultant to complete a Site Inspection (SI) and evaluate hazardous materials at the site. The consultant inspected the site and assigned a U.S. Environmental Protection Agency (EPA) site score of 30.7, making the site eligible for the National Priority List (NPL). The consultant completed a Potential Hazardous Waste Site, Site Inspection Report (EPA Form 2070-13) and notified the EPA of the potential presence of hazardous wastes at the site. To aid in the reclamation effort at the site, the BLM attempted to identify any Potentially Responsible Party (PRP). The site is now abandoned, with Mrs. Richard Valiton shown as the current owner of the patented Londonderry Lode claim. In 1993, the Londonderry Mine adit and associated private tailings areas were included on the Montana Department of State Lands (now the DEQ) Abandoned Hardrock Mines Priority Sites List.

Maxville/Londonderry Mine Reclamation Costs: (Table 1)

Construction Change Orders: (Table 2)

Project Sponsors/Partners: (Table 3)

Reasons for Action: In general, the area is fairly continuously forested and is important habitat for a variety of big game animals, fur bearers, waterfowl, and birds including: mule deer, elk, moose, black bear, beaver, bobcat, and various ducks/geese and mountain grouse. Flint Creek is considered a Class 3 sport fishery which annually receives 192 recreational fishing days per mile.

Arsenic, silver, cadmium, copper, iron, mercury, lead, tin, and zinc were detected at the site at concentrations significantly above background.

According to the human health risk assessment, the primary pathway and contaminant of concern (COC) was arsenic via soil ingestion/dust inhalation. Human ingestion of arsenic via contaminated water or fish was a significant secondary pathway. Reclamation alternatives focused on addressing these exposure pathways.

The environmental risk assessment concluded that lead, copper, and arsenic in soil, water, and stream bed sediments at the site were probably causing adverse health effects to fish, wildlife, and plants. The ecologic risk characterization demonstrated that contaminants at the site constituted a probable adverse ecologic effect via all three exposure scenarios and justified appropriate cleanup.

Objectives: The reclamation project was designed to reduce human, livestock, wildlife, and environmental exposure to the contaminants of concern, as well as reduce the mobility of the contaminants to limit impacts to the local surface water and groundwater.

Pre-Restoration Photos? Yes, see photo at top.

Design Narrative: Three waste rock dumps and two tailings ponds were reclaimed at the site. Waste rock dumps 1 (WR1), 3 (WR3) and 4 (WR4) contained 71,000 yds3, 1,300 yds3, and 750 yds3 of waste material, respectively. Dumps WR1 and WR3 comprised acid producing material, pH of 3.4 and 4.8 for WR1 and pH of 3.5 for WR3. WR1, the largest dump, was actively eroding into Flint Creek for about 400 feet along the bank. Dumps WR1 and WR3 contained antimony, arsenic, barium, copper, iron, lead, mercury, silver, and zinc, at greater than three-times background levels; WR3 contained elevated cadmium concentrations as well. Dump WR4 was vegetated with grasses, willow, alder, weeds, and several lodgepole pine trees, whereas the other 2 dumps were largely barren. Although WR4 contained elevated concentrations of arsenic, lead, mercury, and silver; the dump did not appear to be a major acid producer, as the pH of a sample from it was 6.4. All three rock dumps had low organic matter contents; samples contained 0.2 to 1.1% for WR1, 0.4% for WR3, and 1% for WR4. None of the waste rock dumps were classified as a resource conservation and recovery act (RCRA) hazardous wastes based on the toxicity characteristic leaching procedure (TCLP) analysis. All three waste rock dumps were inaccessible by vehicles because the only road into the remote site came from the other side of the creek. Access roads and a temporary bridge had to be built to allow access into the remote dump sites.

Supplemental Dump Description: (Supplement 2)

Vegetation Survey Table: (Table 4)

Two tailings ponds were located at the site, the first was much smaller than the second. The second tailings pond, tailings pond #2, (TP2) was a large uncontained tailings impoundment located on the east side of Flint Creek. An unknown quantity of municipal solid wastes were intermixed with TP2. In the past, Granite County used the site as a solid waste disposal dumpsite, but the site was closed to dumping in the late 1980's. When the dumpsite was operational, the disposed solid waste was routinely covered and mixed with tailings. The smaller tailings impoundment, TP1, was located approximately 100-feet north of TP2. The volume of TP2 was estimated at 15,700 cubic yards. Concentrations of the following metals were significantly elevated above background (>3X) in the tailings: antimony, arsenic, cadmium, copper, lead, mercury, silver, and zinc. The pH of three separate composite samples of TP2 ranged from 3.9 to 6.7. The tailings material had organic matter content that ranged from 0.2% to 1.8%. TP2 was also not classified as a RCRA characteristic hazardous waste.

Tailings Description: (Supplement 3)

Contaminants of Concern Concentration Tables: (Table 5)

Maxville Bats: (Supplement 4)

Construction Narrative:

The two acid producing waste rock dumps (WR1 and WR3) and both tailings ponds (TP1 and TP2) were excavated, consolidated, and disposed of in a constructed repository. The repository was constructed at the former Maxville solid waste dumpsite located on the east side of Flint Creek (out of the floodplain of Flint Creek). The total area of the repository was approximately 1.13 acres. The repository cap consisted of a geosynthetic clay liner (GCL), geocomposite drainage layer, and a fertilized, seeded, and mulched cover soil layer. Improvements of existing roadways, construction of a temporary bridge across Flint Creek, and construction of a gravel ramp over a set of railroad tracks were all required to allow access for the required equipment to construct the project. Several unstable wooden buildings and structures were dismantled and burned, disposed of, or salvaged by the BLM.

After the specified wastes were excavated and consolidated, the excavations were backfilled with imported cover soil. The backfilled areas were recontoured to match the topography of the surrounding area, and the backfilled areas were then fertilized, seeded, and mulched. Waste sources that were not excavated and hauled to the repository (waste rock dump # 3 [WR3]), were reclaimed in place. WR3 was regraded to match the existing contours (2H:1V maximum slope); lime was then incorporated into the upper 12 inches of the graded material, and imported cover soil was placed over the lime-amended waste rock and this was fertilized and seeded. Erosion control mat was used to minimize erosion potential on all reclaimed slopes steeper than 2.5:1. Erosion control mat was installed over WR3 and the south half of WR1. Areas steeper than 2.5:1 slope were hydroseeded/hydromulched; areas with slopes less steep than 2.5:1 were mulched via crimped straw and were drill seeded. Riparian Areas received seed mix at 21.5 pounds per acre. Semi-Riparian Areas received 22.5 pounds per acre. WR3 and the reclaimed roadways received 27 pounds per acre, and the Waste Consolidation Cap and surrounding areas received 21.5 pounds of seed per acre.

A stream protection structure, consisting of silt fence, two continuous rows of straw bales (one row stacked on top of the other), and sand bags for anchoring the structure, was used to minimize the impact of excavation activities on Flint Creek. After each area had been reclaimed, ditches were constructed to prevent water from running onto the reclaimed areas, and woven wire fences were installed to keep livestock and wildlife out of the newly reclaimed areas. The fences will be removed when the vegetation is well established on each reclaimed area.

The majority of the roads constructed for reclamation purposes were reclaimed after construction was completed. The main site access road remained intact to allow for maintenance and monitoring of the site. The temporary bridge over Flint Creek and the ramp over the railroad tracks were removed when construction was completed.

The contractor utilized from three (3) to fourteen (14) employees on the job site at various times; installation of the stream protection structure was the most labor-intensive task involved with the project. A total of twenty (20) different workers performed different tasks at the site; this number includes the subcontracted seeding crew as well as a Montana Conservation Corp (MCC) crew who were on-site for one week filling sand bags, backfilling an open adit, and assisting with installation of the stream protection structure.

Major Equipment List: (Table 6)

Construction Photos? No

Was this project successful? Yes

Maxville Tailings/Londonderry Mine Site After Reclamation

How was success determined? The site remedial objectives were achieved by removing the solid media waste sources at the site (two uncontained tailings piles and one waste rock dump in close proximity to Flint Creek), containing these wastes via an impermeable, modified RCRA cap, and re-establishing vegetation over the remaining disturbed areas at the site.

The contaminant sources responsible for most severely impacting the Flint Creek drainage have been removed from their unstable locations. The waste sources have been disposed of in an engineered repository, which is protected from erosion, infiltration, and direct environmental contact. Additionally, grading and revegetating of WR3 should significantly stabilize this source by providing an erosion-resistant, vegetated surface that provides protection from surface water and wind erosion and reduces net infiltration through the contaminated media by increasing evapotranspiration processes.

Supplementary Narrative: The following list of comments (in no particular order) addresses how the planning and design for future reclamation projects should be addressed based on lessons learned from the planning, design, and construction of the Maxville reclamation project.

  • Provide detailed specifications for the site topographic map. The specifications should provide for the required scale, contour interval, coordinate system, exact area involved, and the establishment of several benchmarks throughout the work area so that the survey can be reproduced in the field. The Maxville site map (which was developed from a Global Positioning System [GPS] survey) lacked the resolution and precision required for detailed design work. Conventional topographic mapping is preferable over GPS mapping for detailed design work.

  • For reclamation projects of comparable scope and work conditions (e.g., elevation, remoteness, terrain, etc.), the preferred alternative should be selected by about mid-March, so that the detailed design can be completed and the project can be advertised by mid-May, and construction can begin by July 1. The start of the Maxville project was delayed due to pilot-scale testing being conducted on the adit discharge during the spring of 1996; consequently, completion of the project was delayed until late November when winter was in full-force at the site, causing postponement of the final phases of the project until the following spring.

For more information on this project:

The DEQ/MWCB Project Manager, Ben Qui�ones, Solid and Hazardous Waste Specialist, was responsible for coordination of all planning phases for the project, as well as for providing technical and regulatory review during the alternatives evaluation and reclamation design process.

Available Documentation: (Supplement 5)

Submitted by: Montana Department of Environmental Quality

Summarized by:  Mari Reeves

Date: February 19, 2001

ER

Case Histories | Photo Tour | Tech Guide

ER
ER
ER