Ecosystem Restoration ER ER
ER
ER ER
Mineland ER Rangeland ER Storm Water
ER ER ER ER
ER ER
ER
Mineland
ER
Rangeland
Stormwater
ER
ER
Resources
ER
Contacts
ER
Sponsors
ER
ER
ER
ER

ER

Project Name: Douglas Creek Tailings Removal

Project Start Date: July 27, 1998

Project End Date: January 12, 2000

County: Granite

State: Montana

Legal Description: S of the SE of Section 31 and the SW of the SW of Section 32 in Township 7 North, Range 13 West and the NE of the NE of Section 6 in Township 6 North, Range 13 West.

Douglas Creek at beginning of restoration. (taken on July 15, 1998)

Nearest Town and Distance: Philipsburg, Montana is approximately 1.5 miles to the NW.

Location: The Douglas Creek Tailings Site is located adjacent to Douglas Creek along both the east and west banks, in the vicinity of Philipsburg, Montana. The site contains two separate tailings impoundments. The tailings impoundments are located approximately 1.5 miles southeast of Philipsburg.

Estimated Cost: The total cost of the project was $2,458,390. This includes $455,230.00 for engineering (planning, investigation, design, and oversight) and $2,003,160 for construction. The ratio of engineering (total) to construction cost was 22.7%. The ratio of engineering construction management cost to construction cost was 13.4%. To view the engineering cost summary and the engineering/construction change orders for the Douglas Creek restoration click on the icons below.

Engineering Cost Summary: (Table 1)

Engineering/Construction Change Orders: (Table 2)

Project Sponsors: Montana Department of Environmental Quality, Mine Waste Cleanup Bureau and the United States Department of the Interior, Office of Surface Mining.

Oversight Agency: The reclamation project was completed in cooperation with the Montana Department of Environmental Quality, Mine Waste Cleanup Bureau, P.O. Box 200901, 2209 Phoenix Avenue, Helena, MT 59620, Telephone: (406) 444-2074.

Project Partners: Pioneer Technical Services, Inc. (Pioneer), was responsible for planning and providing supporting documentation necessary to provide resource managers with the appropriate decision making tools for full-scale reclamation at the site. Pioneer was also responsible for preparing the final design and engineering specifications for the project, and for overseeing construction. Pioneer's address and telephone is:

Pioneer Technical Services, Inc.
P.O. Box 3445
Butte, MT 59702
Telephone: (406) 782-5177

The project site is owned by Frank Antonioli, Contact Mining Company, 1029 Choteau, Helena, MT 59601.

Reasons for Action: The Douglas Creek Tailings Site is an abandoned hardrock mine site listed on the DEQ/AMRB Priority Sites List. At this site, tailings from the historic Bi-Metallic and Granite Mountain Mills were impounded in the Douglas Creek drainage and were eroding into the creek. The tailings contained elevated levels of arsenic, cadmium, copper, manganese, mercury, lead, antimony, and zinc at concentrations greater than three times background concentrations. Surface water downstream from the site contained elevated arsenic, manganese, lead, and zinc.

Objectives: The purpose of the Douglas Creek Tailings Reclamation Project was to limit human, livestock, wildlife, and environmental exposure to the COCs present at the site (primarily heavy metals) and to reduce the mobility of the contaminants to mitigate potential impacts to local surface water and groundwater resources. This objective was achieved by removing waste from within the stream channel, constructing a stabilized stream, and covering all waste with an impermeable cap and vegetated cover soil.

History of Site: The historic Philipsburg Mining District has produced large quantities of silver, gold, zinc, lead, copper, and most recently, manganese. The first lode was discovered at the Hope Mine in 1864 with other areas following soon after. In 1867, Philipsburg was founded. The period of greatest prosperity for the mining camps of this area was from 1881 to 1893, during which time the Granite Mountain Mine was most productive, and the largest ore bodies of the Bi-Metallic Mines were uncovered.

The tailings at the Douglas Creek Site originated from mine workings at the Bi-Metallic and Granite Mountain Mines located approximately one mile east of the site. The Granite Mountain and Bi-Metallic Mines are located approximately 2.5 miles southeast of Philipsburg on the steep western slope of Granite Mountain. Although they were located on the same ore shoot and controlled from the beginning by practically the same interests, they were worked separately, each with its own reduction plants, until a consolidation was effected in 1898, after which the mines operated as one (USGS, 1913).

The Granite Mountain property was originally located in the fall of 1872, but allowed to lapse periodically until July 6, 1875, when the claim known as the Granite Mountain Lode was located. Charles D. McLure acquired the title in 1880. Prior to this time, little development at the mine had occurred. Originally, the ore was milled at the Algonquin Mill located 1.25 miles northwest of the mine at Hasmark. As exploration reached greater depth and the ore became of higher grade, a dry-crushing stamp mill with a chloridizing roasting furnace was built at the mine. Soon after, a larger mill was built, which provided a total of 80 stamps. From 1885 to 1892, the mining company was extremely prosperous and produced $20,000,000.00 in silver and gold. A third mill with 100 stamps was built 1.5 miles south of the mine at Rumsey. This mill was connected to the mine by a wire tramway, and the railroad at Philipsburg was extended a distance of 7.7 miles to the mill. During the same period, a tunnel was driven 8,500 feet from Rumsey toward the mine.

The Bi-Metallic Mining Co. was organized in 1882, and its plant was similar to that of the Granite Mountain Co. A 100-stamp chloridizing mill was built at the Bi-Metallic Site on Douglas Creek approximately 1.25 miles above Philipsburg. This was connected by rail with the railroad from Philipsburg to Drummond and by wire tramway with ore bins at the hoist house. Water was supplied to these mills by a ditch from Fred Burr Lake located three miles east of the Granite Mine. The production of the mine from 1883 to 1893 totaled approximately $6,000,000.00. Due to the declining price of silver, the mine was shut down in 1893 and remained closed until the consolidation with the Granite in 1898.

Extensive improvements were made after the consolidation. An 8,850-foot tunnel from the canyon of Douglas Creek to the mine was completed. This tunnel drained the Bi-Metallic Mine at a depth of 1,000 feet and the Granite at a depth of 1,450 feet and greatly reduced the cost of pumping. A subsidiary organization, the Montana Water, Electric Power & Mining Co., built the Flint Creek Dam and a hydroelectric power plant, which formed what is now known as Georgetown Lake, to supply the mines and mills with 1,100 horsepower. A 300-ton concentrator, built below the collar of the Bi-Metallic shaft, was the last notable improvement. From 1898 to 1904, production at the mines was steady at approximately $1,000,000.00 annually. In 1901, the company employed 300 men and produced 250 tons of silver ore per day. The mines closed in 1905 due to declining silver prices and decreasing value of the ore. The mines were then reopened in 1906 above the drain tunnel (USGS, 1913).

The mines were worked from five drift tunnels, two deep shafts, and the Douglas Creek tunnel. The Granite shaft was approximately 1,550 feet deep, and the Bi-Metallic shaft was approximately 1,800 feet deep. The vein was stoped as far as 2,600 feet below the surface, and the drifts and crosscuts had a total length of more than 20 miles (USGS, 1913).

USGS 1913 - U.S. Geological Survey, 1913. Geology and Ore Deposits of the Philipsburg Quadrangle, Montana, Professional Paper 78, Written by William Harvey Emmons and Frank Cathcart Calkins, 1913.

Pre-Restoration Photos? No

Design Narrative:

Tailings pond #1 (TP1) is a large uncontained tailings pond located at the west end of the site. Douglas Creek bisects the pond with the majority of the tailings situated on the north side of the creek. In the past, a dam composed of logs and tailings was present at the west end of TP1; at present, this has been breached where Douglas Creek flows through. The face of the dam, as well as the channel of the creek within TP1, are extremely steep and the channel is being actively eroded by the creek.

To determine the extent of metal, arsenic, and cyanide contamination in the tailings, eleven test boreholes were drilled through TP1 to natural soil using a Geoprobe. In addition, two trenches were excavated by hand in the south bank of Douglas Creek within TP1. Based on the X-Ray Fluorescence (XRF) results, a total of sixteen composite samples were submitted to the laboratory from TP1, which included 5 for Target Analyte List (TAL) metals analyses, 3 for Toxicity Characteristic Leaching Procedure (TCLP) metals analyses, 12 for acid base accounting (ABA) and SMP buffer capacity analyses, and 4 for physical and agronomic characteristics. Both the original XRF data and the metal laboratory results indicate that there are three distinct tailings types present in TP1 and can be distinguished by color and/or texture.

Maximum and Average Metals Concentrations in Tailings by XRF Analysis: (Table 3)

Metals Concentrations (mg/kg) - Generalized Layers of TP1 by XRF Analysis (Table 4)

Tailings pond #2 (TP2) is located approximately 1,000 feet upstream of TP1 in Douglas Creek. TP2, like TP1, is a large uncontained tailings pond bisected by Douglas Creek. In the past, TP2 had a dam of logs and tailings on the west end, which has been breached by Douglas Creek. The face of the dam and the banks of Douglas Creek within TP2 are steep. Areas along the creek are being undercut, and there is evidence of recent slumping of tailings into the creek.

A total of five test boreholes were drilled on the north side of TP2 to natural ground using a Geoprobe. In addition, two boreholes were excavated using hand augers on the south side of TP2.

Construction Narrative: Project tasks from July 27, 1998, to October 30, 1998 included completion of stream diversions, construction of sediment ponds, placement of tailings in the lower tailings impoundment, and construction of a portion of the overexcavation/consolidation area at TP2 during this time period.

At the beginning of December 1998, DEQ and Mungas agreed that Mungas could complete the project, during the winter, instead of shutting things down, if they started immediately and worked through the winter and spring months. Mungas began work to complete the project on December 17, 1998. Mungas crews worked more or less continuously, depending on weather and conditions, until January 12, 2000. At that time, all work was completed, except for mulching, willow plantings, and fencing.

At two locations, tailings located within the Douglas Creek floodplain were excavated, removed from the floodplain, and consolidated to one side of the creek. Two consolidation areas were created; these areas included one on the south side of the creek at the lower impoundment (TP1) and one on the north side of the creek at the upper impoundment (TP2). Both consolidation areas were graded and covered with a geomembrane, a drainage layer and two feet of cover soil. A new stream channel was constructed through the excavated areas. Run-on control channels were constructed around the consolidation areas to divert surface water.

Presence of shallow groundwater in the tailings impoundments, construction of the consolidation areas presented challenges for long-term stability of the facility. At TP1, a buttress was constructed to insure slope stability. The buttress consisted of overexcavated and recompacted tailings along the north toe of the consolidation area, underlain by a groundwater interception drain (geocomposite). Additional groundwater interception drains were added to the design during construction to accommodate groundwater in the tailings. These drains, consisting of perforated pipe, drain rock, and geotextile, were placed in the drainages that had originally cut their way through the tailings from the south to the north.

At TP2, the presence of groundwater and saturated, loose tailings, required that all of the tailings on the south side of the creek be overexcavated and recompacted in lifts to form the consolidation area. Prior to replacing the materials, the entire area was underlain by a geocomposite to intercept groundwater.

Areas where tailings were removed received a minimum of one foot of cover soil. All disturbed areas were seeded, fertilized, and mulched.

The reconstruction of the Douglas Creek stream channel was accomplished by constructing steps and pools in the new channel using on-site and imported rocks and boulders. The floodplain was constructed by wrapping seeded cover soil in a woven coir fabric. Willows were to be planted in the fabric. Grade control structures, consisting of a valley-wide trench filled with large rock, were installed at grade changes in the stream to prevent major grade and alignment changes. The stream side of both consolidation areas was protected with riprap and overlain with cover soil.

Three separate seed mixtures (Table 5) were used. Seed Mix #1 for the south-facing slopes and general reclamation areas such as the flat areas and reclaimed roadways and applied at a rate of 46 pounds per acre; Seed Mix #2 was specifically formulated for the north-facing slopes and applied at a rate of 53.5 pounds per acre; and Seed Mix #3 was formulated specifically for the riparian area (reclaimed areas within the floodplain of Douglas Creek) and applied at a rate of 30.5 pounds per acre. The following application rates for seed are based on the drill seeding method. When the broadcast seeding method or the hydraulic seeding method is used, the application rates listed below shall be doubled at no additional cost to the Owner.

Construction Photos: Yes

Douglas Creek during restoration (taken on August 10, 1998)

Douglas Creek during restoration(taken on September 15, 1998)

Douglas Creek towards end of restoration(taken on October 13, 1998)

 

Services/Contractors Used:

Mungas Company, Inc.
P.O. Box 236
Philipsburg, MT 59858
Telephone: (406) 859-3203

Was this project successful? Yes

How was success determined? The Douglas Creek Tailings Site has been reclaimed, and the environmental problems associated with the tailings piles in the creek have been mitigated. The contaminant sources responsible for most severely impacting the Douglas Creek drainage have been isolated from the stream. The waste sources have been consolidated in an engineered repository, which is protected from erosion, infiltration, and direct contact.

Contaminated sediments have not been removed from Douglas Creek downstream of the project site. Remaining sources below the site include the adit discharge and waste rock dump approximately 0.5 mile downstream, which will continue to contribute metals to Douglas Creek.

Supplementary Narrative: The project was completed generally as specified. There were, however, several changes to the design and additions to the project. Significant additions to the original project included the following:

  • addition of groundwater interception drains in the surface water drainage channels at TP1;
  • additional tailings overexcavation for buttress construction at TP1;
  • routing of run-off control ditch at TP1 to the east instead of along the toe;
  • reconstruction of the entire length of stream in the section below TP2;
  • additional tailings overexcavation for the consolidation area at TP2;
  • contractor's decision to add lime to saturated tailings as a drying/placement aid; and changes in the topography of both consolidation areas due to placement of more tailings and lime in TP1 and less in TP2.
  • additional work was planned at the site in the summer of 2000, including willow plantings and mulching. The actual design life of the repositories is not certain; consequently, long-term monitoring and routine inspection and maintenance of the repositories will be needed. Planting of pine seedlings and shrubs on the regraded slopes (except for areas covered with geomembrane) should be considered to allow these areas to naturally blend in with the surrounding environment.

The following is a list of comments that addresses how the planning and design for future reclamation projects should be addressed based on lessons learned from the planning, design, and construction of the Douglas Creek Tailings Reclamation Project.

  • For projects with similar logistical considerations (i.e. consolidation of waste in close proximity, volumes, and space constraints), consider a longer contract time.
  • Require watertight pipe and more stringent installation for stream diversion pipes in anticipation of the potential need for stream diversion longer than one season.
  • Consider specification of lime amendment for saturated tailings as a contingency for material drying and placement.
  • Consider provisions in the contract to allow oversight personnel the authority to limit worker exposure to dust, particularly lime dust.
  • Provide a table of ditch types, rock types, geotextile types in the plans to help clarify specifications.
  • Conduct more laboratory verification samples of geotechnical borings. Include all laboratory data in bid documents.

Jack Yates, Reclamation Specialist, was responsible for coordination of all planning phases for the project, as well as for providing technical and regulatory review during the alternatives evaluation and reclamation design process.

For more information on this project, contact:

Mr. Jack Yates
MDEQ/AMRB
1520 East Sixth Avenue
Helena, MT 59620

Phone: (406) 444-4957

Email: jyates@state.mt.us

Submitted by: Montana Department of Environmental Quality

Summarized by: Mari Reeves, Reclamation Research Unit, Montana State University

Date: 01/29/01

ER

Case Histories | Photo Tour | Tech Guide

ER
ER
ER