Ecosystem Restoration ER ER
ER
ER ER
Mineland ER Rangeland ER Storm Water
ER ER ER ER
ER ER
ER
Mineland
ER
Rangeland
Stormwater
ER
ER
Resources
ER
Contacts
ER
Sponsors
ER
ER
ER
ER

ER

Project Name: Comet Mine Reclamation Project, Phase I

Project Start Date: September 3, 1997

Project End Date: July 8, 1998

County: Jefferson

State: Montana

Legal Description: South ½ of Section 36, Township 7 North, Range 5 West

Nearest Town and Distance: Basin, Montana which lies about six miles to the southwest

Comet Mine Site Before Reclamation Construction

Location: The Comet Mine and Millsite is located in the northeastern part of the Basin/Cataract Mining District in Jefferson County, Montana. The Comet Mine Site is located adjacent to High Ore Creek, approximately six miles northeast of the town of Basin, Montana. The site is located on privately owned, patented mining claims within and bordered by lands administered by the U.S. Department of the Interior/Bureau of Land Management (BLM), Butte District. The site elevation ranges between 6,100 and 6,400 feet above mean sea level.

Project Schedule: The construction phase of the project started on September 3, 1997. Work at the site continued through December 19, 1997, when winter shutdown occurred. The work resumed the following spring, beginning on May 11, 1998 and continued through July 7, 1998. The final inspection was given by the State DEQ/MWCB on July 8, 1998.

Project Costs: The construction cost for the project was $1,268,623.83. Shumaker was awarded the contract with an original bid of $903,580.00; quantity increases and change orders increased the cost by $365,043.83. The total engineering costs associated with the project were $296,967.26.

Project Sponsor(s): Montana Department of Environmental Quality, Mine Waste Cleanup Bureau and the United States Department of the Interior, Office of Surface Mining

Oversight Agency: Montana Department of Environmental Quality, Mine Waste Cleanup Bureau (DEQ/MWCB)

Project Partners: Under contract with the DEQ/MWCB, Pioneer Technical Services, Inc. (Pioneer), was responsible for preparing the final design and engineering specifications for the project, and for overseeing construction. Pioneer performed all quality control activities for the project.

Reasons for Action: Problems at the Comet Mine Site include high concentrations of metals and arsenic in waste materials on-site (mill tailings and waste rock dumps) and in surface water and stream sediments downgradient from the site. Exposed waste materials had potential to result in significant ecological effects. Concern for fisheries, aquatic life, wetlands, terrestrial wildlife, and native terrestrial plant communities has resulted in the remedial actions taken at the Comet Mine and Mill Site. The downstream Boulder River is an important recreational trout fishery. Wetlands of any size are of concern as they can support a diverse ecologic community. Terrestrial wildlife may use this area as part of their summer range, including deer and elk. Wildlife could consume both water and evaporative salts that form on the wastes. This exposure posed a potential for contaminant accumulation and consequent health effects in the wildlife populations that visit the site. Native terrestrial plant communities are notably absent on many of the waste sources at the Comet Site. Native vegetation has not become established on the tailings or the waste rock dumps.

Objectives: The reclamation project was designed to reduce human, livestock, wildlife, and environmental exposure to the contaminants of concern, as well as reduce the mobility of the contaminants to limit impacts to the local surface water and groundwater resources.

History of Site: The Comet Mine is one of the oldest mines in the Basin/Cataract Mining District. It was first mined in about 1880 by the Alta-Montana Mining Company. In 1883, the Alta-Montana Mining Company sold the Comet Mine, the Alta Mine, and several other mines to the Helena Mining and Reduction Company. The majority of the production from the Comet Mine occurred from 1883 to1893 under the Helena Mining and Reduction Company. In 1907, the Montana Consolidated Copper Company deepened the Comet Mine shaft to 600 feet and continued to operate the mine for another 20 years. The Basin Montana Tunnel Company acquired the Comet Mine in 1926 and constructed a 200-ton flotation mill to process Comet ore as well as custom mill ores from other mines in the district. The mill was closed and dismantled in 1941.

The Comet Mine is credited with production valued at $13,000,000 prior to 1911. Since 1902, the Comet Mine has produced 496,000 tons of ore, yielding 42,000 ounces of gold; 3,000,000 ounces of silver; 28,000,000 pounds of lead; 23,000,000 pounds of zinc; and 2,000,000 pounds of copper. The mine consists of a 900-foot vertical shaft with drifts at nine levels. In total, the mine comprised 20,000 feet of lineal workings.

Site Description: The Comet Mine Site encompasses an area of approximately 35 acres, and includes two tailings impoundments located in the High Ore Creek floodplain, three waste rock piles (two of which are in the floodplain), five waste rock dumps on Silver Hill, a large open pit mine area, and numerous abandoned buildings and structures associated with the mine and the town of Comet. The mill tailings deposits have been eroding into the creek for many years. Mitigation measures have been completed on the site in the past, primarily to minimize contact between High Ore Creek and the tailings deposits. In 1990, the Montana Department of Fish, Wildlife and Parks (MDFWP) sponsored reconstruction of a pre-existing creek diversion around the waste rock piles and mill tailings, and sedimentation ponds to control the release of mine waste sediments from the tailings impoundments into High Ore Creek. Most recently, DEQ/MWCB initiated interim reclamation activities at the site to improve sediment and erosion control of the tailings deposits.

The Comet Mine is located on a mountainous hillside. Shrubland, riparian, and timbered plant communities occur at the mine site. The potential natural community of the shrubland is Artemisia tridentata/ Agropyron spicatum. The potential for the timbered areas is Pseudotsuga menziesii/ Calamagrostis rubescens. No sensitive, threatened, or endangered plants were found on-site. The following four species of noxious weeds occur at the site: Musk thistle, Canada thistle, Spotted knapweed, and Dalmatian toadflax. None of these occur in populations large enough to be considered infestations. Riparian areas occur along High Ore Creek. The riparian zone below the mine site is a Populus tremuloides/Poa pratensis community type. The riparian area above the mine site is a Populus tremuloides/Cornus stolonifera habitat type. Both communities have been heavily browsed and contain early seral species. The riparian area above the mine is functioning, but at risk due to grazing pressure. Below the mine, the riparian area is not functioning because of tailings in the stream channel and grazing. Where the creek has been diverted, no riparian community exists along the new channel.

Waste Sources: The Comet Mine Site was divided into two distinct subunits based on the waste types, locations, and applicable reclamation technologies. These subunits consist of: 1) the solid media, including waste rock dumps and tailings ponds, and 2) the aqueous media, which encompasses adit discharges, seepage, and drainage water.

Waste Rock Dump #1 (WR1) was located on the southside of the High Ore Creek diversion, to the west of the lower pit, and has an estimated volume of 142,000 cubic yards (cy). Waste Rock Dump #1 (WR1) covered an area of approximately 14,200 square yards with steep and high banks along the entire west end. Waste Rock Dump #1 (WR1) was accessible by vehicles and comprised one of the largest waste volumes. Waste Rock Dump #1 (WR1) was one of the most significant sources of COCs (Contaminants of Concern) to the surface and ground water. Concentrations of the following metals were significantly elevated above background (>3X) in the dump: antimony, arsenic, cadmium, copper, lead, manganese, silver, mercury, and zinc. Waste Rock Dump #1 (WR1) was considered a potential acid producer and approximately 70 tons of lime per acre would have been required to successfully establish vegetation on this material, assuming a 12-inch depth of incorporation. The pH ranged from 4.2 to 7.2 in the five separate test pits samples from WR1. According to the TCLP data obtained for WR1, the concentration of lead measured in laboratory-generated leachate exceeded the regulatory limit for hazardous waste classification.

Waste Rock Dump #2 (WR2) was also located to the south of the High Ore Creek diversion and to the southwest of WR1. This dump was estimated to be 85,000 cy, a little more than half the size of WR1, and covered an area of approximately 10,200 square yards. Waste Rock Dump #2 (WR2) was relatively devoid of vegetation and the west bank was steep and high. Waste Rock Dump #2 (WR2) was easily accessible by vehicles. Concentrations of the following metals were elevated above background (>3X) in the dump: antimony, arsenic, cadmium, copper, manganese, lead, mercury, silver, and zinc. The pH ranged from 5.7 to 7.0 in samples taken from the three separate test pits. According to the TCLP data obtained for WR2, concentrations measured in laboratory-generated leachate did not exceed the regulatory limit for hazardous waste classification.

Waste Rock Dump #3 (WR3), located east of the upper pit, was the largest dump with an estimated volume of 150,000 cy and covered an area of approximately 16,300 square yards. The dump was both steep and high, with some vegetation on the surface. Vehicles were able to access the top of this dump. Waste Rock Dump #3 (WR3) was the source area of least concern, primarily because it was isolated from both surface water and ground water. Concentrations of the following metals were elevated above background (>3X) in the dump: arsenic, cadmium, copper, lead, manganese, mercury, silver, and zinc. The pH ranged from 5.6 to 6.8 in samples obtained from the three separate test pits. According to the TCLP data obtained for WR3, concentrations measured in laboratory-generated leachate did not exceed the regulatory limit for hazardous waste classification.

Tailings Pile #1 (TP1) was located east of WR2 and extended beneath WR1. Tailings Pile #1 (TP1) had a volume estimated at 38,500 cy of material and covered an area of approximately 7,650 square yards. There was no vegetation on TP1 and it is accessible to vehicles. Tailings Pile #1 (TP1) and TP2 were the largest source areas of concern, primarily because they were located in the floodplain of High Ore Creek. Concentrations of the following metals were elevated above background (>3X) in the pile: antimony, arsenic, cadmium, copper, iron, lead, manganese, mercury, silver, and zinc. The fire assay tests conducted on three discrete samples from TP1 detected gold concentrations at 0.09 oz./ton, 0.102 oz./ton, and 0.116 oz./ton. The pH measured ranged from 5.2 to 6.0 in the test pit samples. According to the TCLP data obtained for TP1, concentrations measured in laboratory-generated leachate did not exceed the regulatory limit for hazardous waste classification.

Tailings Pile #2 (TP2) was located west of TP1 and extended beneath WR2. Tailings Pile #2 (TP2) was the largest waste source, with an estimated volume of 158,000 cy of material, and covered an area of approximately 18,950 square yards. There was some vegetation on TP2 and it was accessible to vehicles. Concentrations of the following metals are elevated above background (>3X) in the dump: antimony, arsenic, cadmium, copper, iron, lead, manganese, mercury, silver, and zinc. The fire assay tests conducted on samples from TP2 detected gold concentrations at 0.021 and 0.029 oz./ton. The pH was measured from <3.5 to 7.0 in the test pit samples.

Six separate waste rock dumps with a combined estimated volume of 2,000 cy are located on Silver Hill. The majority of the rock volume is in the two lower waste rock dumps. All of the waste rock dumps are north of the main road on the south slope of Silver Hill. The lower two waste rock dumps are the only dumps accessible by vehicle. Concentrations of the following metals are significantly elevated above background (>3X) in the dumps: antimony, arsenic, cadmium, copper, lead, manganese, silver, and zinc. The ABA and SMP buffering capacity results indicate that the Silver Hill waste rock dumps are considered potential acid producers and approximately 12 tons of lime per acre would be required to successfully establish vegetation on this material, assuming a 12-inch depth of incorporation. The pH value was 5.2 for the composite sample. According to the TCLP data obtained for the Silver Hill waste rock dumps, concentrations measured in laboratory-generated leachate did not exceed the regulatory limit for hazardous waste classification.

Waste Source Characteristics for the Comet Mine Site: (Table 1)

Contaminant Concentrations for the Comet Mine Site: (Table 2)

Effects on Surface Water: A downstream surface water sample in High Ore Creek had total metals concentrations greater than three times an upstream sample concentration for the following elements: arsenic, barium, cadmium, copper, iron, lead, magnesium, manganese, silver, and zinc. The downstream sample exceeded the following water quality standards: Maximum Contaminant Levels (MCLs) for arsenic, cadmium, antimony, lead, and zinc; acute and chronic aquatic life standards for arsenic, cadmium, antimony, lead, and zinc; and chronic aquatic life standards for iron and mercury. Montana Human Health Standards (HHSs) were exceeded for antimony, arsenic, cadmium, iron, lead, manganese, and mercury. Comparing total metals to the dissolved metals at the downstream station shows the following distribution: 9% of the arsenic, 56% of the cadmium, 2% of the copper, 9% of the iron, 0% of the lead, 20% of the antimony, and 80% of the zinc are in the dissolved phase.

The sediment sample downstream in High Ore Creek had total metals concentrations greater than three times the background soils concentrations for the following elements: arsenic, cadmium, copper, lead, manganese, mercury, silver, and zinc.

Two groundwater discharges potentially associated with mine workings were identified and characterized during this sampling episode. A sample of a spring at the base of the diversion channel dike, probably associated with an adit discharge from the Silver Hill area, and a sample of water emanating from the ground within the northern-most erosion channel in the lower tailings exceeded MCLs for arsenic and cadmium, and Montana HHSs for arsenic, cadmium, iron, lead, manganese, and mercury. Comparing total metals to the dissolved metals for the two water samples shows the following metals are in the dissolved phase: arsenic - 82% and 85%, cadmium - 100% and 93%, copper - 75% and 7%, iron - 96% and 88%, lead - 45% and 2%, and zinc - 97% and 97%, respectively. Intermediate samples taken downgradient of these two samples generally show lower concentrations of dissolved phase metals and higher concentrations of the solid phase (particulate) metals.

Water Quality and Sediment for Comet Mine Site: (Table 3)

Comet Mine Site Prior to Reclamation Construction, Phase I

Construction Narrative: The purpose of the Phase I Comet Mine Reclamation project was to excavate Tailings Piles #1 and #2 and Waste Rock Dumps #1 and #2 and dispose of them in the open pit located on the east side of the site. The wet tailings were to be disposed of in the deepest portion of the pit on the east side, and dry tailings and waste rock were to be disposed of in the shallower west section of pit or the bench area in the north section of the pit. Sediments contained in Settling Pond #1 were to be completely excavated and disposed of in the open pit. A portion of the High Ore Creek diversion embankment was to be excavated and disposed of in the shallower areas of the pit. Run-on control ditches (type A, B and C) were to be constructed to protect excavated areas from erosion.

Prior to Change Order #1, WR3 was to be excavated (approximately 35,000 cubic yards) and graded to attain target maximum slopes of 2H:1V. Excavation of WR3 was to be used to form an interim final cover over the consolidated mine wastes in the pit. The dump was to be then amended with lime and compost, fertilized and seeded, and covered with erosion control mat. Change Order #1 instructed the Contractor to remove the entire amount of waste rock from WR3 and dispose of it in the repository. Waste Rock Dump #3 (WR3) was also to be enclosed by a wire fence after revegetation procedures were complete.

Phase I of the project was completed over two construction seasons. The majority of the waste removal and placement was done during the 1997 construction season (September through December). The remaining work was completed in the early months of the 1998 construction season (May through July).

Items completed during the 1998 construction season: (Table 4)

Phase I of the Comet Mine Reclamation Project is 100 percent complete. Most of the contaminant sources that were responsible for negatively impacting the High Ore Creek drainage have been permanently removed, which alleviates the majority of the environmental problems associated with the site. The repository was constructed by backfilling the upper and lower pits with the waste material. The existing High Ore Creek diversion ditch to be removed in Phase II of the Comet Mine Reclamation Project overlies a considerable amount of tailings; however, a portion of these tailings were removed during Phase I. The WR3 area is back to its original native slopes; compost, fertilizer, seed, and erosion control mats were added to the slope. When last observed in July 1998, the WR3 area contained a significant amount of vegetation.

Comet Mine Site Under Reclamation Construction, Phase I, View 1

Comet Mine Site Under Reclamation Construction, Phase I, View 2

Services/Contractors Used: The Contractor utilized from seven (7) to eighteen (18) employees on the job site at various times. The majority of the labor involved with this project was in the removal of the tailings and waste rock which took two to three excavators, three to four haul trucks, four scrapers and two to four dozers. A team of four people was brought in to construct the ditches. The fencing was contracted out to Smith River Fencing of White Sulphur Springs, Montana. Other employees on site included the superintendent, mechanic, construction company owner, and project manager (on occasion).

The successful low bidder for the project construction was Shumaker Trucking and Excavating Contractors, Inc. Contact information is:

Shumaker Trucking and Excavating Contractors, Inc.
P.O. Box 1279
Great Falls, MT 59403
Telephone: (406) 727-3537

Was this Project Successful? Yes

Comet Mine Site Reclamation Project Before and After Restoration.

Before Restoration

After Restoration

Supplementary Narrative: Final inspection and approval was conducted on July 8, 1998. Attendance included Ben Quiìones and John Koerth of DEQ/MWCB, Gene Shumaker of Shumaker, and Dawn Clark and Steve Pierce of Pioneer. All construction activities were approved except for the following items: 1) the east side of the fence surrounding WR3 needed an additional panel and a deadman; and 2) straw bales placed on the buttress slope of the repository needed to be restaked.

Other issues involved with the site reclamation activities included the following:

  1. Equipment would often get stuck in the saturated tailings in the drainage area and upper pit causing some delays in the project. On October 10, the Contractor had four pieces of equipment stuck at the same time, which delayed the job for almost an entire day.  In order to attain the moisture specification for the tailings placed in the repository, the Contractor continuously mixed the wet tailings with dry waste rock or dry tailings. Moisture tests were taken with a nuclear density gauge. To attain the moisture specification, the tailings had to be within 4% over the optimum moisture content of 19%; as it turned out, the material had to be significantly less than 19% before the equipment could operate in it.

  2. Engineers also decided that it would be better to go with dozer basins on a covered waste rock pile, instead of run-on control ditches as originally planned. 

  3. Some scrap metal at the site was found to be radioactive by the steel mill, to which it was sent, in Salt Lake City, Utah.

For more information on this project, contact:

Mr. Ben Quiìones
MDEQ/MWCB
2209 Phoenix Avenue
Helena, MT 59620

Phone: (406) 444-2074

Email: bequinones@state.mt.us

Submitted by: Montana Department of Environmental Quality

Summarized by: Mari Reeves, Reclamation Research Unit, Montana State University

Date: 12/03/00

ER

Case Histories | Photo Tour | Tech Guide

ER
ER
ER