|
Brooklyn Mine Restoration Project
July 17,
1995
October 6,
1995
Granite
Montana
46° 23' 25"
113° 07' 30"
|
 |
| Brooklyn
Mine waste dumps about Boulder Creek prior to remediation |
|
Nearest Town and Distance: Maxville, MT. Approximately 7
miles northwest.
Location: The project site is located adjacent to Boulder
Creek, a tributary to Flint Creek, in the Philipsburg Ranger District
of the Deerlodge National Forest, Granite County, Montana. The site
is in the S 1/2 of the NE 1/4 of Section 5, Township 7 North, Range
12 West. To reach the site, turn east off State Highway 1 at Maxville,
a small community located 9 miles north of Philipsburg, Montana.
Then, travel 7 miles southeast along the Boulder Creek Road (Forest
Route 676).
Project Cost: The construction cost for this project was
$767,895. The original bid was $728,223 with two change orders issued
for an additional $45,208 and a decrease in costs for $5,536. Four
qualified bidders responded with bids ranging from $728,220.36 to
$1,038,000.00. The Engineer's estimate was $854,787.50. To see a
table of construction cost bids broken down by task, click on the
link below.
Construction Cost Bids for Brooklyn Mine Restoration Project (Table
1)
The total engineering cost for this project was $236,380. It cost
$52,131 to prepare the Work Plan, Field Sampling Plan, and other
supporting documents for both the Brooklyn and Nonpareil Sites.
The reclamation investigation and risk assessment for the Brooklyn
and Nonpareil Sites cost $57,217. Preparation of the Expanded Engineering
Evaluation/Cost Analysis for the Brooklyn Site cost $34,600. Engineering
design and bid specification preparation cost $42,372. Construction
management including engineering administration and inspection cost
$50,060. Construction of the Boulder Creek Stream Diversion Structure
cost $25,441.
Costs associated with work plan preparation and site characterization
are higher than typically expected due to the inclusion of another
site, the Nonpareil Site, during this phase of the project.
The total project cost was $1,029,717.
Project Sponsor(s): Montana Department of Environmental
Quality, United States Department of the Interior/Office of Surface
Mining
Oversight Agency: Montana Department of Environmental Quality
Project Partners: The United States Forest Service, Pioneer
Technical Services, the Montana Department of Environmental Quality/Abandoned
Mine Reclamation Bureau, and Environmental Reclamation Northwest,
LLC.
Contact Information: (Table
2)
Reasons for Action: Soils, surface waters, and ground water
had been contaminated by heavy metals in waste rock dumps and tailings
ponds from the Brooklyn and Nonpareil Mines. The concentrations
of the following metals are significantly elevated above background
at the mine sites: arsenic, silver, barium, cadmium, copper, mercury,
molybdenum, lead, antimony, and zinc. The toe of one of the larger
waste rock dumps at the Brooklyn Mine was in Boulder Creek, and
thus was affecting surface water directly. One of the waste rock
dumps and the snow-melt runoff from one of the tailings ponds exceeded
the TCLP value of 5.0 mg/l for lead.
Numerous ecologic receptors were identified as potentially affected
by site contamination. Fisheries, aquatic life, and wetlands were
of concern because the mine site was adjacent to Boulder Creek and
was adversely affecting water quality downstream. Boulder Creek
was identified by the USFS as a Bull trout and Cutthroat trout fishery.
Although information from the USFS indicated that habitat in Boulder
Creek was suitable to support a Cutthroat fishery below the mine,
the creek below the Brooklyn Mine did not contain Cutthroat trout.
It is not clear whether the Cutthroat fishery was impacted because
of the toxicity of the water or stream sediments released from the
site, or for some other reason. Wetlands of any size were of concern
as they can support a diverse ecologic community. Terrestrial wildlife
that may use this area as part of their summer range, including
mule deer and elk were potential receptors of contamination. There
is evidence of use of the upper dump by elk, both for water and
possibly for consuming evaporative salts that form on the waste
piles. Mine wastes posed a potential for contaminant accumulation
and subsequent health effects in the big game populations that visited
the site. Native terrestrial plant communities were notably absent
on many of the waste sources at the Brooklyn Mine site.
Objectives: The purpose of this reclamation project was
to limit human and environmental exposure to the contaminants of
concern and reduce the mobility of these contaminants to mitigate
impacts to the local surface water and ground water resources.
History of Site: Important hardrock mining discoveries were
initially made in the Boulder Creek drainage above the town of Princeton
in 1885. The period of greatest prosperity for the area was from
1881 to 1893. The major metal commodities were silver, zinc, lead,
and copper (USGS 1913).
The Brooklyn Mine, located on the south slope of Pierre Hill, was
initially known as the Pierre Mine. A 600-foot adit was driven northward
through limestone and shales at the Brooklyn Mine site to intersect
a porphyry dike 500 feet from the portal. The dike trended southeastwardly
and was reportedly exposed in two shallow pits located below the
mine. The porphyry carried abundant pyrite and locally contained
nodules of rich lead ore. The minerals present included quartz,
barite, sphalerite, galena, and lead and copper carbonates. Considerable
ore was mined from a shaft located above the adit; the ore was presumably
a deposit in limestone. Ore from the Brooklyn Mine was usually shipped
to Helena for smelting. The main target metal was silver; however,
the mine also produced a small amount of gold. An 80-ton shipment
from the mine in 1907 averaged 37 ounces of silver, 13 percent zinc,
8 percent lead, and 1.7 percent copper. The Brooklyn Mine was operated
briefly from 1913 to 1914 after a 100-ton selective flotation mill
was constructed on the property. The mill was reportedly destroyed
by fire in 1939.
From 1945 to 1948, Saranac Mining, owned by various Spokane mining
interests, operated the Brooklyn Mine property and began actively
reworking the mine. In addition to the Brooklyn Mine, Saranac Mining
reopened the Nonpareil Mine in 1947 and constructed a mill on the
property. The mill reportedly had a capacity of 150 tons-per-day.
The mill equipment included a 75 horsepower motor, a 100-ton ball
mill, classifiers, two selective flotation batteries of 12 cells
each, filters, and other various machinery. The mill was designed
to pass ore through automatically by gravity. Although the mill
was constructed on the Nonpareil property, historical accounts speculate
that most of the ore developments were at the Brooklyn Mine.
USGS 1913 - U.S. Geological Survey, 1913. Geology and Ore Deposits
of the Philipsburg Quadrangle, Montana, Professional Paper 78, Written
by William Harvey Emmons and Frank Cathcart Calkins, 1913.
Site Description: Seven discrete sources were characterized
at the Brooklyn Mine site, including six waste rock dumps and one
tailings pond.
Waste rock dump #1 (WR1) actually consisted of two separate
dumps located high on the ridge east of Boulder Creek. The two dumps
were located in a heavily timbered area within approximately 350
feet of each other. The volume of the two dumps identified collectively
as WR1 was estimated at 9,050 cubic yards. The lower, smaller dump
had a small pit associated with it, and the upper, larger dump had
a 20-feet tall highwall located adjacent to it on the uphill side.
Waste rock dump #1 represented the uppermost (highest elevation)
waste source associated with the Brooklyn Mine site. The dumps ranged
in lateral distance from approximately 1,150 to 1,445 feet east
of Boulder Creek; and elevations ranged from 6,410 to 6,490 feet
above mean sea level (approximately 435 feet higher in elevation
than Boulder Creek at its closest point).
Waste rock dump #2 (WR2) was located lower on the ridge
and slightly northwest of WR1. The dump was situated on a steep
section of the ridge and appeared to be relatively shallow (probably
no more than four or five feet deep at the deepest point). Along
with being extremely steep, the surface of WR2 was extremely hard
crusted (cemented) due to the abundance of carbonate material (calcite).
Abundant wooden debris were also scattered throughout the dump,
and a collapsing wooden loadout structure was located on the south
side of the dump. Waste rock dump #2 was located approximately 950
feet east of Boulder Creek at an elevation of 6,340 feet (approximately
280 feet higher in elevation than Boulder Creek at its closest point).
The volume of WR2 was estimated at 3,900 cubic yards.
Waste rock dump #3 (WR3) was a large dump located directly
south of WR2. The top surface of this irregularly shaped dump was
quite flat; however, the side slopes break off at sharp angles (angle
of repose) on the relatively steep ridge and created a deep accumulation
of material (approximately 25 feet deep at the deepest point). Similar
to WR1 and WR2, the surface of WR3 was hard crusted. Also, abundant
wooden debris was scattered throughout the dump, and a collapsing
wooden loadout structure was located on the southeast side. Waste
rock dump #3 was located approximately 750 feet east of Boulder
Creek at an elevation of 6,280 feet (approximately 215 feet higher
in elevation than Boulder Creek at its closest point). The volume
of WR3 was estimated at 14,670 cubic yards.
Waste rock dump #4 (WR4) was a small and somewhat indistinct
dump located adjacent to a trench approximately 80 feet southeast
of WR1 (high on the ridge east of Boulder Creek). The dump was indistinct
because vegetation (including grasses, weeds, and abundant young
conifers) was well established on most of the dump's surface. Waste
rock dump #4 was located approximately 1,450 feet east of Boulder
Creek at an elevation of approximately 6,490 feet (435 feet higher
in elevation than Boulder Creek at its closest point, and one of
the highest waste sources associated with the Brooklyn Mine site).
Waste rock dump #5 (WR5) was a large dump located adjacent
to Boulder Creek. The dump was situated on the steep east bank of
Boulder Creek, and the toe of WR5 extended into the active section
of the stream channel for approximately 250 feet along the bank.
The dump was being actively undercut by the stream. The preliminary
risk analysis conducted for the Brooklyn Mine site using the Abandoned
or Inactive Mine Scoring System (AIMSS) concluded that surface water
is the primary pathway of concern at the Brooklyn Mine site (specifically,
the Boulder Creek Fishery) and that WR5 was, by far, the primary
source area of concern due to its perceived risk of contributing
to surface water degradation. The volume of WR5 was estimated at
10,930 cubic yards. The pH of a composite sample of this section
of the dump was 7.4. The underlying soil has elevated concentrations
of several elements found within the dump that are fairly mobile
in the pH regime of WR5, including: cadmium, copper, and zinc. The
concentrations of these three elements in the underlying soil were
higher than those found in the dump itself, indicating that significant
leaching of these more mobile elements had occurred.
Waste rock dump #7 (WR7) was a relatively small and indistinct
dump located adjacent to Boulder Creek approximately 1,000 feet
downstream from the main Brooklyn Mine. The dump was located approximately
70 feet east of Boulder Creek at an elevation of 5,970 feet, and
was discovered while collecting surface water samples in Boulder
Creek; the dump was not previously inventoried or mapped. The dump
was indistinct because vegetation (including grasses, weeds, and
a few young conifers) is well established on most of the surface.
The volume of WR7 was estimated at 200 cubic yards.
Tailings pond #1 (TP1) was a constructed tailings impoundment
located on a timbered bench halfway between the upper Brooklyn Mine
workings and Boulder Creek. The impoundment was positioned near
the top edge of the steep east canyon wall which drops off sharply
toward Boulder Creek. The elevation of the tailings impoundment
was 6,180 feet, which placed it approximately 125 feet higher in
elevation than Boulder Creek. At its closest point, Boulder Creek
flowed within approximately 200 feet of the tailings. An intermittent
drainage, which originated near a breached berm on the northwest
edge of the tailings impoundment, provided a direct pathway for
tailings-laden runoff to reach Boulder Creek. The volume of TP1
was estimated at 3,700 cubic yards. Cyanide was detected in one
of the six composite 0-6" samples at the detection limit; cyanide
was not detected in the remaining samples. The soils immediately
underlying the tailings had elevated concentrations of several metals
found in the tailings. Deeper underlying soils, at a depth of 1.5
feet beneath the tailings, had elevated concentrations of copper
and zinc. The elements found in the underlying soils were at a much
lower concentration than those found in the tailings.
Metals present in the source materials are presented in the source
areas table. To view the source characteristics table for the Brooklyn
and Nonpareil Mine sites click on the link below.
Source Characteristics for Brooklyn Mine and Nonpareil Mine Sites:
(Table
3)
Metals concentrations were elevated in both the water and sediments
in Boulder Creek, below the mine site, and in various surface water
samples flowing through, or standing near, the waste materials.
The following Montana Numeric Water Quality Standards were exceeded
in Boulder Creek during the remedial investigation: the acute aquatic
life criteria for silver; the chronic aquatic life criteria for
mercury (the chronic aquatic life criteria for mercury may have
been exceeded at other sample locations as well, however, since
the chronic criteria for mercury is actually less than the detection
limit, it is impossible to determine this); and the chronic aquatic
life criteria for lead. These exceedences of Water Quality Standards
were directly attributable to the Brooklyn Mine. The chronic aquatic
life criteria for mercury was exceeded in a small pond located high
on the ridge above the Brooklyn Mine, adjacent to WR1. Several federal
and state water quality standards were exceeded in a sample, which
was taken from an intermittent drainage that originates near a breached
berm on the northwest edge of the tailings impoundment and provides
a direct pathway for tailings-laden runoff to reach Boulder Creek.
The water quality standards exceeded in this runoff sample include:
Maximum Contaminant Levels (MCLs) were exceeded for cadmium and
antimony; Montana acute aquatic life criteria were exceeded for
cadmium, copper, lead, and zinc; and Montana chronic aquatic life
criteria were exceeded for cadmium, copper, lead, zinc, antimony,
and mercury.
Phase partitioning was determined in the tailings snowmelt runoff.
To review this partitioning table for runoff click on the link below.
Phase Partitioning Tailings Snowmelt Runoff for the Brooklyn Mine
Site: (Table
4)
The Nonpareil Mine Site was included in the investigation portion
of this project, but no remedial activities were performed at this
site due to property ownership issues. The Nonpareil Mine Site comprised
one waste rock dump and five tailings ponds near Boulder Creek.
The volume of the Nonpareil waste rock dump was estimated at 3,500
cubic yards. The volume of tailings pond 1 was estimated at 645
cubic yards. The volume of tailings pond 2 was estimated at 20 cubic
yards. The volume of tailings pond 3 was estimated at 35 cubic yards.
The volume of tailings pond 4 was estimated at 325 cubic yards.
The volume of tailings pond 5 was estimated at 9,060 cubic yards.
Metals present in the wastes at the Nonpareil Mine Site are shown
in the source areas table.
 |
| Waste
Rock Dump along Boulder Creek Drainage before restoration |
Permitting Narrative: A 124 permit was required for this
project.
Construction Narrative: The Brooklyn Mine Reclamation Project
consisted of providing all labor, materials, earthwork, and incidentals
to construct a waste repository; demolish and dispose of one metal
building and miscellaneous debris; excavate, transport, and dispose
of approximately 18,300 bank cubic yards of waste rock and mill
tailings in the waste repository; recontour, topsoil, and revegetate
the excavation areas; recontour, apply soil amendments, topsoil,
and revegetate three additional waste rock dumps; and reconstruct
approximately 525 feet of stream bank and fish habitat features.
A stream diversion structure was necessary to isolate Boulder Creek
from the waste rock excavation activities. Due to the tight time
frame associated with this project, the stream diversion structure
was procured and installed by Pioneer with the assistance of the
Montana Conservation Corp. Construction of the Boulder Creek stream
diversion structure was initiated on July 17, 1995; continued on
July 18, 19, 20, 24, 25; and was completed on July 28, 1995.
The diversion structure was constructed from half-round 36-inch
diameter corrugated metal pipe. The pipe was raised slightly above
the creek bed on jack-leg supports at ten foot centers to maintain
a constant seven percent grade. A small dam was constructed at the
inlet to divert the majority of the flow of Boulder Creek into the
pipe.
The reclamation plan involved removing those waste sources, which
were the principal sources of concern at the Brooklyn Mine (the
tailings pond and waste rock dump #5) and disposing of these wastes
in a constructed repository. The repository was constructed on the
bench area located directly south of waste rock dump #3. The repository
bottom consists of a single geosynthetic clay (GCL) bottom liner
with an integral drainage layer and a low maintenance leachate collection
and removal system. A secondary layer of B-Grade (off-specification)
GCL was installed to protect the primary liner from potential chemical
reaction. The total surface area of the repository required to contain
the specified wastes is approximately 1.5 acres. Approximately 3.0
acres of timber was removed to accommodate repository construction
and removal of tailings dispersed throughout sparsely timbered areas.
After the specified wastes were loaded and compacted in the repository,
a multi-layered, lined cap was constructed overlying the wastes,
and the cap was fertilized, seeded, and mulched. The excavated areas
(tailings and waste rock dump #5 locations) were backfilled to contours
matching the surrounding topography, fertilized, seeded, and mulched.
The stream channel adjacent to waste rock dump #5 was be reconstructed
in a step-pool configuration similar to the undisturbed stream channel
located upstream of the project. Excess soil originating from the
repository excavation was amended with compost and used as cover
soil in the excavated areas. In addition, a subsurface limestone
french drain was constructed below the adit located at waste rock
dump #5 to treat a minor intermittent adit discharge.
The other large waste rock dumps located at the site (waste rock
dumps #1, 2, and 3) were graded out to approximately match the surrounding
topography. Lime was incorporated into the upper 12-inches of the
dump material, as needed. The dumps were covered with soil (previously
amended with compost), fertilized, seeded, and mulched in place.
Excess soil from the repository excavation was also used to cover
the waste rock dumps. Slopes flatter than 2.5:1 were mulched by
crimping straw and drill seeded. Slopes steeper than 2.5:1 were
hydroseeded with a mixture of wood fiber mulch, seed, fertilizer,
and tackifer. Additionally, biodegradable erosion control mat (straw/coconut
fiber woven mat) was installed on slopes steeper than 2.5:1 following
the hydroseeding procedures.
Trees and shrubs (dogwood, alder, Lodgepole, and willows) were
placed along creek, slides off road, and toe of hill at WR5, after
which these areas were hydroseeded.
Ditches were constructed to divert run-on away from each of the
reclaimed areas and the repository. Temporary fences were constructed
to surround each of the reclaimed source areas as well as the repository
cap to allow for the establishment of vegetation without interference
from livestock or wildlife. Several of the temporary roads constructed
at the site were obliterated and reclaimed; however, some of the
roads remain intact to allow access for monitoring the progress
of the reclaimed areas (and maintenance when necessary) for a period
of one to several years.
 |
| Brooklyn
Mine Site construction along Boulder Creek Drainage. (photo
taken by Pioneer Technical Services, Inc., Butte, Montana) |
 |
| Boulder
Creek immediately after coversoil placement. (photo taken by
Pioneer Technical Services, Inc., Butte, Montana) |
 |
| Brooklyn
Mine Site construction along Boulder Creek Drainage |
Suppliers/Products Used:
EKO Compost
P.O. Box 9168
Missoula, MT 59807
Ph.: 406-721-1423
FAX: 406-721-7526 |
Montana Limestone Products
283 Shannon Road
Laurel, MT 59044
Big Horn Limestone |
Bentomat GCL for the
repository bottom
Geonet and filter fabric (geocomposite)
Silva fiber wood mulch |
A list of heavy machinery used during construction is available
here: (Table
5)
Services/Contractors Used: A total of thirty (32) different employees
worked on the Brooklyn Project including Environmental Reclamation
Northwest, LLC (ERNW address noted above) permanent and temporary
employees and subcontractors. The typical daily crew consisted of
the foreman, two or three excavator operators, a bulldozer operator,
three to five dump truck drivers, and three to ten laborers. Occasionally,
appropriately skilled laborers would be used to operate the front-end
loader, skid loaders, the vibratory roller, or the motor grader:
(Table
6)
Was This Project Successful? Yes
Boulder Creek Drainage at the Brooklyn Mine Site.
 |
| Before
Restoration |
 |
| After
Restoration |
The Brooklyn
Mine Site has been completely reclaimed and the hazards associated
with the site have been mitigated. Vegetation was sparse during
the first growing season. A reclamation success evaluation was conducted
by the Reclamation Research Unit at Montana State University during
the summer of 1998 at the request of the Forest Service. Management
recommendations were made to enhance the seeded vegetation and control
the encroachment of weeds.
 |
| Poor
vegetation establishment on waste repository following restoration |
 |
| Good
vegetation response in the southeast end of the tailings pond |
 |
| Boulder
Creek Drainage immediately following restoration. (photo taken
by Pioneer Technical Services, Inc., Butte, Montana |
 |
| Evaluation
of streambank erosion occurring on the Boulder Creek Drainage
near the Brooklyn Mine Site three years after restoration |
Supplementary Narrative: A final field inspection was conducted
by Jack Yates (MDEQ/AMRB) on October 13, 1995. The Final Completion
date is one year from the Substantial Completion date or October
13, 1996.
The project went as scheduled with few modifications. The primary
change was the removal of dry tailings from the Nonpareil Site for
disposal in the Brooklyn Repository and reclamation of the areas
from which tailings were removed.
The site will be checked in the spring of 1996 and periodically
thereafter for revegetation success. The USFS has committed to an
aggressive program to obliterate spotted knapweed that was present
on the site prior to reclamation construction.
Additional planting of riparian vegetation, shrubs, and trees will
be conducted in the spring of 1996.
The USFS has also committed to monitoring stream water quality
above and below the site and the leachate from the repository.
The following suggestions are intended to help prevent minor problems
from recurring on future projects.
The Brooklyn project contract contained one critical milestone
date. All WR5 removal and stream reconstruction activities had to
be completed by September 15, 1995, in order to comply with the
terms of the 124 permit. The bid specifications stated that this
work must be completed by September 15, 1995, but there was no penalty
if this date was not met. The possibility of writing stipulated
penalties on intermediate contract dates into the contract to help
motivate contractors to meet these types of deadlines should be
evaluated.
The MDEQ/AMRB contract should require that signed copies of the
contractor's daily log sheets be provided to the inspector on a
daily basis to circumvent the potential for differing interpretations
of the daily activities.
Stormwater/temporary erosion control standard specifications need
to be improved. Standard drawings are necessary. A requirement that
the contractor have someone on-site during precipitation events
to maintain BMP's is also necessary. The contractor must have an
adequate supply of temporary erosion control materials on-site prior
to breaking ground. The weed-free certification requirement for
straw bales used for temporary erosion control was not included
in the standard language in the specifications package -- this requirement
is imperative. In addition, the substitution certified weed-free
hay grass bales for certified straw allows the possible introduction
of undesirable non-native perennial grass species such as Timothy
and Crested wheat grass. Requiring that the contractor identify
a source and procure straw, and making it clear the hay grass substitutions
will not be allowed should mitigate this problem.
A bid item for run-on/run-off ditches as needed with a standard
specification would be helpful. The standard boiler plate storm
water language currently in the specifications implies that additional
ditches may be required and should be considered incidental. This
may not be very fair to the contractor in complex drainage areas.
Pioneer needs to better classify excavation/borrow after a final
repository location is selected, for design purposes so that the
design engineer can anticipate potential problems and design accordingly.
This will require a small amount of additional field work following
the EE/CA (approximately six test pits per acre). The USFS and MDT
have suggested that this data should not be provided in the bid
package or to the prospective contractors and that work of this
type should be described simply as "Unclassified Excavation"
or "Unclassified Borrow." This may result in bidding higher
unit prices, but may balance out in the end by negating any potential
for change of condition claims.
Pioneer provided the contractor with consolidation boundary stakes
and preliminary cut/fill stakes for the waste rock dumps to be graded
out. These stakes did not seem to help the operators and promoted
some confusion on the steep grades. Specifying the target slopes
and outlining the approximate consolidation boundaries on the plans
should supply the contractors with sufficient information to conduct
the work.
The GCL specified for the repository was versatile and relatively
easy to install. The second layer of GCL on the bottom of the repository
specified to mitigate potential chemical compatibility problems
was more difficult to install. Alternatives to this approach such
as a light synthetic liner should be evaluated in the future.
The "Design Quantity" classification worked very well
on the tailings and waste rock excavation bid items as well as the
reclamation area bid items. The only conflict resulted from absence
of bank and loose designations from the quantities in the bid package.
Excavation volumes should be labeled as bank in the plans to avoid
claims.
Testing for liming requirements following the grading of dumps
was very important to the final product. Waste rock dumps are extremely
heterogeneous in nature, making it nearly impossible to characterize
the entire contents during the investigation stage of a project.
Liming requirements will be better characterized in the future.
Pioneer falsely assumed that average values determined from the
investigation would be adequate. Testing after regrading indicated
scattered hot spots. The liming rate had to be increased to neutralize
the hot spots even though the average rate was lower than specified.
The specification used by Pioneer for organic amendment of soil
was lacking in detail. The contractor spent considerable effort
trying to find an acceptable "equal" and became frustrated
that Pioneer repeatedly turned down his requests based on parameters
that were not detailed in the specifications. In the future, Pioneer's
specifications will include an acceptable range for the carbon to
nitrogen ratio, organic carbon content, allowable metals content,
physical parameters, and a weed seed free specification. Additional
pre-approved sources may also be helpful.
Compost analyses performed during construction included moisture
content on the compost and organic carbon content on the mixed soil.
The moisture contents were necessary to verify that the volume of
compost supplied to the contractor by EKO Compost of Missoula corresponded
to the dry weight Pioneer specified. Compost moisture contents increased
by several percentage points following rain events. The organic
carbon content analysis was necessary to verify that the compost
mix ratio was adequate and that mixing was consistent. A possible
modification to Pioneer's specification would be to specify the
target organic content of the mixed soil and give an approximate
dry weight and volume of compost plus the approximate mix ratio
to accomplish the target organic content. This approach would negate
the need for conducting moisture content analyses.
The contractor had difficulties obtaining some of the specified
native species seeds. Pioneer contacted seed companies prior to
finalizing the Bid Package to make sure that seed was available,
but by the time the contractor placed an order, some species were
sold out. MDEQ/AMRB may want to require that seed is ordered within
10 days following notice to proceed.
Revision of the temporary fence specification provided by the USFS
is recommended to make the fence more economical and constructible.
The MDEQ/Air Quality Bureau recently began enforcing a law requiring
a permit for burning of all demolition debris. When necessary, the
burning permit should be obtained in advance of letting the project,
due to the long public comment period required.
Either the contractor or engineer should be required to provide
usable communications (cellular or radio phones) on remote project
sites. Many difficulties that occurred during the first two weeks
of the project could have been easily resolved if there had been
a phone on-site.
For more information on this project, contact:
Mr. Jack Yates
MDEQ/AMRB
1520 East Sixth Avenue
Helena, MT 59620
Phone: (406) 444-4957
Email: jyates@state.mt.us
Submitted by: Montana Department of Environmental Quality
Summarized by: Mari Reeves, Reclamation Research Unit, Montana
State University
Date: 11/29/00
|