Ecosystem Restoration ER ER
ER
ER ER
Mineland ER Rangeland ER Storm Water
ER ER ER ER
ER ER
ER
Mineland
ER
Rangeland
Stormwater
ER
ER
Resources
ER
Contacts
ER
Sponsors
ER
ER
ER
ER

ER

Project Name: Bonnanza Mine

Project Start Date: 1986

Project End Date: 1996

County: Baker

State: Oregon

Latitude: N 44° 59' Longitude: W 117° 05' 12"

Mining in the background and reclamation in the foreground

Nearest Town and Distance: Approximately 10 road miles northwest of Halfway, Oregon.

Estimated Cost: Not Applicable.

Project Sponsor(s): Bonnanza Mining Company

Oversight Agency: Oregon Department of Geology and Mineral Industries (DOG AMI)

Project Partners: Oregon Department of Fish and Wildlife

Reasons for Action: To profitably recover gold and successfully reclaim the site while meeting all water quality discharge requirements.

Objectives: To return the entire site to a safe and useable condition after completion of placer mining.

History of Site: Bonnanza Mining Company began mine development in 1986 on patented land adjacent to Pine Creek. Approximately 10 of the 45 acres mined by Bonnanza had been mined prior to 1940 and left unreclaimed. Bonnanza moved approximately 1.3 million yards of overburden consisting of glacial till, landslide deposits, and stream gravels and about 335,000 cubic yards of gold bearing gravel.
Early mining efforts had been partially thwarted by huge boulders scattered through the glacial gravels. Historic surface and drift mining left considerable reserves in the ground.

The site is located on the floor of a very steep-sided valley vegetated with mixed conifers. Snow accumulations of over 100Ó per year are not unusual. Maintaining water quality in Pine Creek and tributaries that crossed the site presented major hurdles to successful mining. Due to the heavy snowfall, mining was restricted to summer and early fall.

Permitting Narrative: The lead permitting agency was DOGAMI which issued on operating permit for gold mining after approval of a reclamation plan and acceptance of an appropriate reclamation bond. Storm water and process water discharges to Pine Creek were monitored under a National Pollution Discharge Elimination System (NPDES) permit issued by the Oregon Department of Environmental Quality (DEQ). The US Army Corps of Engineers and the Oregon Department of State Lands issued permits for the relocation of Pine Creek. Mining operations are an allowed use on patented mining claims in Baker County so a Conditional Use Permit was not required.

Design Narrative: Mining began in the center of this long but narrow valley floor since that was the location of the previously mined but not reclaimed area where much of the overburden had already been removed. The mine plan called for concurrent reclamation. As mining progressed upstream, the mined-out areas were backfilled first with the largest rocks and then with progressive smaller material. Next, sand and silt-laden wash water from the processing plant was allowed to flow into the backfilled area to fill the voids between the larger rocks. Using this method, in conjunction with hydrocyclones to separate silt from the waste stream, a much smaller than normal system of settling ponds was required.

Even in areas that were not previously mined salvageable topsoil was insufficient for covering the entire site. Therefore a topsoil substitute was created from sand and silt from the processing plant discharge which was mixed with straw and manure. The straw and manure were obtained from local farmers and ranchers in exchange for truckloads of washed gravels. A local nursery was hired to establish native species on the site.

Stream diversions were designed and constructed by Bonnanza in close cooperation with the Oregon Department of Fish and Wildlife and the advice of a stream geomorphologist. The post-mining stream channels are stable and at a gradient equal to or less than that found prior to the start of the Bonnanza mining.

Upon completion of mining, 41 acres were reclaimed to forestland, 2 acres were wetlands, and 2 acres were stream banks and riparian lands.

Construction and Post-Mining Narrative: Reclamation began shortly after mining began, was continuous during mining and continued after mining was completed. Each area covered with soil material during the summer was mulched and seeded prior to arrival of the autumn snow. Large woody debris was placed perpendicular to the slopes to control runoff and create mirco-habitat for plants and animals. Over 5,000 mixed conifers were planted. In addition, dogwood, black cottonwood, chokecherry, wild rose, snowberry, willows and alders were propagated on-site. Two wetland areas were created by exposing shallow depressions in the underlying bedrock and allowing water to pond there.

Construction Photos? Yes

The mobile dredge used for gold recovery is in the background while the foreground shows reclamation in progress

Bonnanza Mine under reclamation construction

Services/Contractors Used: Lidstone and Associates from Ft. Collins Colorado supplied consulting services on stream geomorphology issues.

Was this project successful?: Yes

How was success determined?: Visual observation suggests that the timber productivity and wildlife habitat are both greater than before mining began. The success of the erosion control was demonstrated by the clarity of water in Pine Creek during periods of storm water runoff from the site. The success of the ponderosa pine revegetation is shown in the accompanying photograph of trees taken about 5 years after planting. Great Blue Herons have been observed feeding on the abundant tadpoles growing in the wetland areas.

Post-construction photographs: Yes

Deep Creek after relocation

Ponderosa Pine on reclaimed ground

Slopes before reclamation

Slopes after reclamation

Supplementary Narrative: The National Association of State Land Reclamationist issued their annual reclamation award to Bonnanza Mining for their work on the site. Tom Bonn was president of Bonnanza Mining and directed the on-site operations; Terry Drever-Gee was the Environmental Coordinator for Bonnanza. E. Frank Schnitzer was the responsible reclamationist for DOGAMI throughout most of the mining and reclamation phases. Bonnanza Mining Company has subsequently been dissolved.

For more information on this project, contact:

Dawn Marshall
Oregon Department of Geology and Mineral Industries
1536 SE Queen Av.
Albany, OR 97321

Phone: (541) 753-1804

E-mail: dawn.m.marshall@state.or.us

Available Documentation: Numerous inspection reports are in DOGAMI file 01-0146

Submitted by: Allen Throop, Consultant

Date: January 2001

ER

Case Histories | Photo Tour | Tech Guide

ER
ER
ER