Ecosystem Restoration ER ER
ER
ER ER
Mineland ER Rangeland ER Storm Water
ER ER ER ER
ER ER
ER
Mineland
ER
Rangeland
Stormwater
ER
ER
Resources
ER
Contacts
ER
Sponsors
ER
ER
ER
ER

ER

Project Name: Alta Mine Remediation Project

Project Start Date: July 2, 1999

Project End Date: December 20, 1999

County: Jefferson

State: Montana

Latitude: 46° 22' 24" Longitude: 112° 05' 12"

Alta Mine Site, circa 1890

Nearest Town and Distance: 1.5 miles SW of Corbin, MT

Estimated Cost: The total project construction cost for the Alta Mine Lower Waste Rock Dump reclamation project was $944,321.35. Construction costs included an initial bid of $624,266.00, with four change orders resulting in an increase of $319,095.35.

The total engineering cost for the project, including site characterization and environmental investigation, was $279,612.00. Costs associated with the preparation of the reclamation work plans (PRC Environmental Management, Inc. [PRC] 1996a) and final sampling and analysis plans (PRC 1996b) for the Alta Mine were $38,868.00. Costs for conducting and reporting the reclamation investigation were $72,079.00. These investigation costs included the hydrogeologic investigation (PRC 1997a). The expanded engineering evaluation/cost analysis (EEECA) for the Alta Mine (PRC 1997b and PRC 1998) cost $34,408.00. Costs for engineering design and bid specification preparation cost, including additional site characterization, (TtEMI 1999) were $42,422.00. Construction inspection and management costs were $91,835.00.

Project Sponsor(s): Montana Department of Environmental Quality, United States Department of the Interior, Office of Surface Mining

Oversight Agency: Montana Department of Environmental Quality

Project Partners: PRC Environmental Management Inc. prepared the Reclamation Work Plans, the final Sampling and Analysis Plan, the Hydrogeologic Investigation, and the Expanded Engineering and Cost Analysis. Tetra Tech Environmental Management Inc. performed the Engineering Design and Bid Specification, which included additional site characterization.

Reasons for Action: Heavy metal contamination and acid production from mine waste rock piles were affecting surface water and ground water resources at the site, as well as potentially exposing humans, wildlife, and plants to toxins in the wastes. Previous surface water samples indicated elevated levels of antimony, arsenic, cadmium, copper, iron, lead, mercury, and zinc (Pioneer 1993). The primary contaminants of concern at the Alta Mine Lower Waste Rock Dump were arsenic, lead, and manganese. The maximum measured arsenic concentration was 4,400 parts per million (ppm) and the mean detected concentration was 1,063 ppm. The maximum measured lead concentration was 7,745 ppm and the mean detected was 3,238 ppm. The maximum measured manganese concentration was 4,765 ppm and the mean detected was 1,711 ppm.

Objectives: The primary objective of the Alta Mine Lower Waste Rock Dump reclamation project was to protect human health and the environment in accordance with the guidelines set forth in the National Contingency Plan (NCP). Specifically, the reclamation action selected was implemented to limit human and environmental exposure to the contaminants of concern and reduce the mobility of those contaminants to prevent impacts to local surface

History of Site: The Alta Mine site is an abandoned hardrock silver mine listed on the Montana Department of Environmental Quality, Abandoned Mine Reclamation Bureau (DEQ/AMRB) priority sites list. Shortly after the ore body at the Alta Mine was discovered in 1869, the property was sold to the Alta Montana Company. In 1883, the property was purchased by the Helena Mining and Reduction Company (also known as the Helena and Livingston Smelting and Reduction Company) which operated the mine until 1896. During operation of the mine by the Helena Mining and Reduction Company, between 150 and 200 tons of ore were mined per day. At the same time, a concentrator was constructed in Corbin, approximately 1.5 miles northwest of the Alta Mine. In 1896, all mining operations at Alta ceased.

The Alta Mill Site drainage before remediation

Some time after the closing of the mine, a concentrator was constructed at the Alta Mine site (Roby and others 1960). In 1909 the mine was purchased by the Boston and Alta Company (also known as the Boston and Alta Mining Company). The Boston and Alta company sunk the Level No. 8 shaft, also known as the Dick shaft, 665 feet. In 1925, the Boston and Alta Company constructed a second concentrator about one mile east of Corbin to treat the Alta mine tailings a third time. The tailings were later hauled to Corbin Flats (Deckler 1982). The Boston and Alta Company operated the mine until 1929. The mine was leased to the Knickerbocker Mines Company in 1929 (Roby and others 1960). In the late 1930s, much of the tailings at Corbin Flats were hauled to the American Smelting and Refining Company in East Helena.

Some time after 1949, the mine was leased to Ed Lahey (Lahey Leasing Company) who operated an open cut on the vein on the crest of Alta Mountain. From 1950 through 1956 the Lahey Leasing Company mined low-grade ore from the upper mine area. This low grade ore was used as silica flux in the smelter at East Helena.

Prior to 1893, it is estimated that the mine produced more than 1.25 million tons of ore. Between 1901 and 1948, another 10,000 tons of ore were produced.

Site Description: The Alta mine area was divided into the Upper Mine Area and the Lower Mine Area. The volume of waste rock materials associated with the open pits in the upper mine area was first estimated at 163,755 cubic yards (yd3). The actual volume of waste rock was difficult to estimate because the dumps were located on steep slopes, and the depth to bedrock varies significantly across the site. The upper mine covered an area of 494,406 square feet (ft2) (11.35 acres). The lower mine area contained a waste rock dump, several adits, and one shaft. The volume of waste in the lower mine area was estimated to be 151,502 yd3, and covered an area of 171,626 ft2 (3.94 acres).

Surface water at the site was shown to contain elevated concentrations of heavy metal contaminants of concern. Previous analyses of water from the discharge indicated very low pH (acidic) levels as well as elevated metals concentrations. Previous surface water samples indicated elevated levels of antimony, arsenic, cadmium, copper, iron, lead, mercury, and zinc (Pioneer 1993).

Reconstructed stream channel at the Alta Mine following removal of waste material.
The rip-rap stream channel is protected from sediment by straw bales.
Terrace remain (upper left) where waste materials were removed at the Alta Mine remediation project.

Surface water and depth to ground water were characterized at the site during the reclamation investigation and the hydrogeologic investigation. The main adit for the Alta Mine, adit Level No.8, was located adjacent to the partially-collapsed hoist house. No acid mine discharge was observed flowing from the adit during the Spring 1996 field investigations. Depth to water measured in the shaft during Spring 1996 was approximately 6 feet bgs. Water infiltrating through the mine workings and from the shaft was likely recharging the waste rock pile and was a source for the acid rock drainage. Acid generation probably occurred within the sulfide-rich underground workings and the waste rock pile. This acid probably leached metals from the exposed wall rock and waste rock pile. Surface water at the Alta Mine site is present in both the upper and lower mine areas. The east side open pit contains a minor seep that is acidic and appears to be associated with a collapsed adit. This seep may have been a recharge area for the underground workings, although its location near the ridge suggests that it is only seasonally present. The lower mine area contains a significant discharge of water from the waste rock pile located in the drainage.

Permits that may have been required to complete this project. (Table 1)

Construction Narrative: Site reclamation involved removal of the waste rock, which was considered the principal source of concern, from the Alta Mine Lower Waste Rock Dump. These wastes were then placed in a repository constructed approximately 1 mile southeast of the Alta mine site. The Alta Gulch surface water drainage was reconstructed through the former waste rock dump site and lined with riprap. A total of seven straw bale barrier sediment traps were constructed to reduce the quantity of residual wastes that might erode onto and from the reclaimed area. Final reclamation construction activities consisted of the following work: constructing access roads; clearing and grubbing the work site; dismantling and salvaging the mine headframe; constructing a 5.7 acre mine waste disposal repository; excavating, transporting, and disposing of 154,000 cubic yards of mine waste in the repository; sealing the mine shaft; reconstructing 900 linear feet of surface water drainage; constructing 2,239 linear feet of diversion ditches; benching and topsoiling (6,000 cubic yards) the former waste rock dump site; applying and grading 19,000 cubic yards of cover soil on the repository; fertilizing, seeding, and mulching 13 acres of excavation and construction areas; constructing 4,727 linear feet of fences; and transporting 7,500 cubic yards of excess cover soil to the repository site.

Construction of a mine waste repository at the Alta Mine near Jefferson City, Montana. Placement of waste is occurring on top of a clay fabric and drainage geogrid

Dozer pushes mine waste toward the edge of the repository liner. Multiple geosynthetic fabrics were used in construction including a basal clay fabric and overylying drainage grid

The repository was constructed on United State Bureau of Land Management (BLM) property approximately one mile southeast of the Alta Mine . The total footprint area of the repository required to contain the specified wastes was approximately 5.72 acres. Upon removal of topsoil from the repository area, clean native soil was then excavated to form the base of the repository. The base of repository was completed using a geocomposite clay liner and leachate collection system composed of a geocomposite filter fabric and leachate collection piping. After the specified wastes were deposited and compacted in the repository, a multi-layered lined cap was constructed overlying the wastes, and the cap was seeded and mulched. Excavated material unsuitable for use in the repository cap was used to backfill old exploration pits and to reduce the slope break on the northwest end of the repository. Ditches were constructed to divert runon and runoff away from the repository. A 6-foot high woven-wire fence was constructed to surround the repository to limit access by people and allow for the establishment of vegetation without interference from livestock or wildlife. In addition, a 4-wire barbed-wire fence was constructed around the perimeter of the reclaimed waste rock dump area to control livestock grazing until the revegetation became established. Temporary roads constructed at the site were reclaimed immediately after the mine reclamation activities were completed.

Services/Contractors Used: The successful low bidder for the construction project was Smith Contracting Inc. (Contractor) of Whitehall, Montana. The project manager for Smith was Lee Barron. The on-site superintendent was Dave Smith. Smith¥s address is as follows:

Smith Contracting, Inc.

1118 Highway 55
Whitehall, Montana 59759
(406) 287-3048

Project Success: Yes
The Alta Mill Site drainage before remediation

Alta Mill Site drainage following remediation

How was success determined? The reclamation of the Alta Mine Lower Waste Rock Dump was successfully completed. All work was completed within the change order modified contract period (one field season) and within the Engineer's cost estimate.

Supplementary Narrative: The site elevation is 5600-6200 ft asl. Depth to water varies from 9 to 121 feet below ground surface (bgs). Groundwater measurements in the open shaft in the lower mine area indicate water can be as high as 6 feet bgs. During construction, several issues developed that required extra effort by the State, Engineer, and Contractor to resolve. These issues included the presence of four large concrete foundations buried within the waste rock dump; the inability to completely backfill the mine shaft due to a blockage located only 35 feet below ground surface; and most significantly, the greater than anticipated volume of waste rock. All of these issues were resolved during construction.

For more information on this project, contact:

Mr. Dale Herbort
MDEQ/MWCB
P.O. Box 200901
Helena, Montana 59620-0901


Phone: (406) 444-1294

Fax: (406) 444-0443

Email: dherbort@state.mt.us

Available Documentation: (Table 2)

Submitted by: Montana Department of Environmental Quality

Summarized by: Mari Reeves, Reclamation Research Unit, Montana State University

Date: 11/26/00

ER

Case Histories | Photo Tour | Tech Guide

ER
ER
ER